Monday, October 26, 2020

Cost Accounting - Contract Costing

 

Cost Accounting

CONTRACT COSTING


Part A: Discussion of basic theories including Tables, Formats and different Formulas

Part B: 16 Illustrations with Solutions


Part A



              Construction site

Introduction

 

Contract Costing or Terminal Costing as it is often termed, is a variant of the job costing system, which is applied in businesses engaged in building or other construction work. The jobs are usually the contracts entered into with the customers. As the number of such contracts handled at a time by a business may not be usually large, Contract Costing is comparatively simpler in operation than job costing system. The basic principles applied in Contract Costing are the same as those used in job costing except that these are modified to suit the particular requirements of the contracts.

 

Contract Costing is a type of costing used in construction activities such as construction of buildings, roads, bridges etc. The person who takes contract for a price is called the Contractor and the person from whom it is taken is called the Contractee. We are mainly concerned with the books of the contractor. To find out profit earned or loss incurred on the contract, the contractor prepares a nominal account in his books called ‘Contract Account’. In this account, all the expenses incurred by the contractor are debited and the income i.e. mainly work certified is credited; the difference represents profit or loss.

 

The items generally debited are materials, wages, establishment expenses & other expenses. Depreciation of assets used in the contract will also be debited, but unlike in other types of accounts it is customary in Contract Accounts to debit the opening balance of the assets and credit the closing balance of the same instead of depreciation, wherever it is convenient to do so. Amounts credited are work-in-progress, which consists of value of work certified and cost of work not certified and any scrap of materials etc.

 

The contracts usually run for a number of years; however it is necessary to find out the profit or loss at the end of every year. The profit earned on a Contract Account is primarily called Accounting Profit or Notional Profit. A portion of the Notional Profit is kept as work-in-progress provision and the other portion is transferred to Profit & Loss Account. The profit to be transferred to Profit & Loss Account out of the Notional Profit is ascertained by taking into consideration the degree of completion of the work, cash received etc.


Click here for "Format of Contract Account" in PDF


Profit to be transferred to Profit and Loss Account

 

If there is any contract which is incomplete at the end of the financial year, profit on such incomplete contract is also considered for the purpose of profit and loss account subject to some restrictions. Usually, only a part of such profit on incomplete contract is transferred to profit and loss account. But if there is a loss on incomplete contract, the whole of the loss is debited to profit and loss account.

 

The guidelines in this regard are as follows:

 

1. If the contract is completed 25% or less no profit is transferred to profit and loss account.

 

2. If the contract is completed above 25% but below 50%, profit to be transferred to profit and loss account is –

Notional profit x (Cash received ÷ Value of work certified) x 1/3

 

3. If the contract is completed 50% or more but less than 90%, profit to be transferred to profit and loss account is –

Notional profit x (Cash received ÷ Value of work certified) x 2/3

 

4. If the contract is almost completed (i.e. 90% or more), profit to be transferred to profit and loss account should be calculated on the basis of estimated total profit in any of the following two ways:

 

 First alternative (if not specifically instructed to follow the second alternative)

Profit to be transferred to profit and loss account =

Estimated total profit x (Cash received ÷ Contract price)

 

 Second alternative (to be applied only when there is specific instruction)

Profit to be transferred to profit and loss account =

Estimated total profit x (Value of work certified ÷ Contract price)

 

Here, Estimated Total Profit

= Contract price – Estimated total cost of completion of the contract

= Contract price − (Total cost up-to-date + Estimated further cost)

 

  Important Notes:

1.

Percentage completion =

(Value of work certified ÷ Contract price) x 100

 

2. Balance of the Accounting / Notional Profit, after proportionate profit is transferred to P/L A/c, will be transferred to WIP Provision Account.

 

3. If there is a notional loss on incomplete contract, the whole of the loss is transferred to profit and loss account.

 

4. If in any problem estimated further cost to complete the contract is given, profit to be transferred to profit and loss account should be calculated on the basis of estimated total profit only. In such cases percentage completion of the contract has to be ignored. In other words, even if the percentage completion of the contract is less than 90%, if the estimated further cost to complete the contract is given in the problem, profit to be transferred to profit and loss account should be calculated on the basis of estimated total profit.

 

5. When the completion of contract is 90% or more, but the estimated further cost to complete the contract is not given in the problem, profit to be taken to profit and loss account should be calculated by using the following formula:

 

Profit to be transferred to profit and loss account =

Notional profit x (Value of work certified ÷ Contract price)

 

Work-in-Progress (WIP)

Work-in-progress can be calculated by using any of the following two formulas:

 

1

WIP =

 

Cost of work done + Profit transferred to profit and loss account

2

WIP =

 

Value of work certified + Cost of work not certified – WIP Provision

 





                         Construction site


 Part B


Contract Costing

Selected Problems



Illustration: 1

A contractor commenced the work on a particular contract on 1st April, 2018 and he usually closes his books of accounts on 31st December of each year. The following information is revealed from his costing records on 31st December, 2018.

 

Rs

Materials sent to site

43,000

Jr. Engineer

12,620

Labour

1,00,220


A machine costing Rs 30,000 remained in use on site for 1/5th of year. Its working life was estimated at 5 years and scrap value at Rs 2,000. A supervisor is paid Rs 2,000 per month and had devoted half of his time on the contract. All other expenses were Rs 14,000 and the materials on site were Rs 2,500.

The contract price was Rs 4, 00,000. On 31st December, 2018 2/3rd of the contracts were completed. However, the architect gave certificate only for Rs 2, 00,000 on which 80% was paid.

Prepare Contract Account.

 

Solution: 1

                                                              Contract account

Particulars

Rs

Particulars

Rs

To D/Materials sent to site

43,000

By D/Materials at site

2,500

To D/Labour

1,00,220

By Value of work certified

2,00,000

To Dep. on machinery

    [(30,000 – 2,000) × 1/5 × 1/5]

 

1,120

By Cost of work not certified

     [W.N. 1]

 

44,365

To Jr. Engineer

12,620

 

 

To Supervisor [2,000 × 9 × ½ ]

9,000

 

 

To Other expenses

14,000

 

 

To Notional Profit c/d

66,905

 

 

 

2,46,865

 

2,46,865

To P/L a/c         [W.N. 3]

35,683

By Notional Profit b/d

66,905

To WIP Provision (b/f)

31,222

 

 

 

66,905

 

66,905

 

Working notes:

1.    Computation of cost of work not certified

 

Rs

Total cost incurred up to 31.12.2018

1,77,460

Proportion of total contract completed up to 31.12.2018

2/3

Estimated total cost to complete the contract      (1,77,460 × 3/2)

2,66,190

Proportion of total contract certified up to 31.12.2018

½

Proportion of estimated total cost certified up to 31.12.2018

½

Cost of work certified         (2,66,190 × ½ )

1,33,095

Cost of work not certified  (1,77,460 – 1,33,095)

44,365

 

2.    Percentage Completion

= (Value of work certified ÷ Contract Price) × 100%

= (Rs 2, 00,000 ÷ Rs 4, 00,000) × 100%

= 50%

 

3.    Profit to be transferred to P/L A/c

= Notional Profit × (Cash Received ÷ Value of work certified) × 2/3

= Rs 66,905 × (Rs 1, 60,000 ÷ Rs 2, 00,000) × 2/3

= Rs 35,683

 

Illustration: 2

The following figures are supplied to you by a contractor for the year ending 31st December, 2018:

Particulars

Rs

Work-in-Progress on 31-12-2017                                                 Rs 85,000

 

Less: Cash received from contractee                                           (Rs 55,000)

30,000

During the year:

 

Wages

8,500

Materials bought

6,000

Working expenses

1,500

Materials issued from stores

10,500

Administrative expenses ( Rs 250 are chargeable to P and L A/c )

1,250

Plant

2,500

Material returned to supplier

450

Material returned to stores

550

Work certified

15,000

Contracts finished       (Work certified and handed over to contractee)

22,500

Profits taken upon contracts

11,500

Advances from contractee

40,000

 

Prepare the Contract Account and the Contractee’s, and show the work-in-progress as it would appear in the Balance sheet.

 

Solution: 2

                                                      Contract account

Particulars

Rs

Particulars

Rs

To Opening WIP

85,000

By Materials returned (450 + 550)

1,000

To D/Materials (6,000 + 10,500)

16,500

By Value of work certified

15,000

To D/Wages

8,500

By Contractee A/c

22,500

To Working expenses

1,500

By Cost of work not certified (b/f)

88,000 

To Administrative expenses

1,000

 

 

To Plant (Depreciation)

2,500

 

 

To P/L A/c

11,500

 

 

 

1,26,500

 

1,26,500

 

                                                    Contractee account

Particulars

Rs

Particulars

Rs

To Contract A/c

22,500

By Balance b/d

55,000

To Balance c/d (Balance of cash received as advance)

72,500

By Cash

40,000

 

95,000

 

95,000

 

                             Balance Sheet as at................               (Extract)

Liabilities

Rs

Assets

Rs

 

 

Closing WIP    (W.N.)    1,03,000

 

 

 

Less: Cash received          72,500

          (as advance)

30,500

 

 

 

 

 

Working notes:

Value of closing work-in-progress

= Value of work certified + Cost of work not certified – WIP Provision

= 15,000 + 88,000 – Nil

= Rs 1, 03,000

 

Illustration: 3

A firm of engineers undertook three contracts beginning on 1st Jan, 1st May and 1st August 2018. Their accounts on 30th November, 2018 showed the following position:

Particulars

Contract I

Contract II

Contract III

 

Rs

Rs

Rs

Contract price

80,000

54,000

60,000

Materials

14,400

11,600

4,000

Wages

22,000

22,500

2,800

General expenses

800

550

200

Cash received for work certified

30,000

24,000

5,400

Work certified

40,000

32,000

7,200

Work uncertified

1,200

1,600

400

Wages outstanding

700

750

350

General expenses outstanding

150

100

50

Plant installed

4,000

3,200

2,400

Materials on hand

800

800

400

 

On the respective dates of the contracts, the plant was installed depreciation thereon being taken at 15% p.a. You are required to prepare the Contract Accounts.

 

Solution: 3

                                                          Contract accounts

Particulars

I

II

III

Particulars

I

II

III

 

Rs

Rs

Rs

 

Rs

Rs

Rs

To D/Materials

14,400

11,600

4,000

By D/Mat. on hand

800

800

400

To D/Wages

    (Including o/s)

22,700

23,250

3,150

By Value of work

     Certified

40,000

32,000

7,200

To Gen. Expenses

    (Including o/s)

950

650

250

By Cost of work

     Not certified

1,200

1,600

400

To Dep. on Plant

    [W.N. 1]

550

280

120

By P/L A/c (Loss

     Transferred)

 

1,380

 

To Notional profit

3,400

 

480

 

 

 

 

 

42,000

35,780

8,000

 

42,000

35,780

8,000

To P/L A/c [W.N. 3]

1,700

 

 

By Notional profit

3,400

 

480

To WIP Provision

1,700

 

480

 

 

 

 

 

3,400

 

480

 

3,400

 

480

 

 

 

 

 

 

 

 

 

Working notes:

1.    Depreciation on plant

Contract I

Rs 4,000 × 15% × 11/12

Rs 550

Contract II

Rs 3,200 × 15% × 7/12

Rs 280

Contract III

Rs 2,400 × 15% × 4/12

Rs 120

 

2.    Percentage completion

Contract I

(Rs 40,000 ÷ Rs 80,000) × 100%

50%

Contract II

Not required, because incurred loss

 

Contract III

(Rs 7,200 ÷ Rs 60,000) × 100%          

12%

 

3.    Profit to be transferred to P/L A/c

Contract I

3,400 × (30,000 ÷ 40,000) × 2/3

Rs 1,700

Contract II

Entire loss transferred to P/L A/c

 

Contract III

Percentage completion is less than 25%

Nil

 

Illustration: 4

The following is the Trial Balance of Premier Construction Company, engaged on the execution of contract No.747, for the year ended 31st December, 2018.

Particulars

Debit (Rs)

Credit (Rs)

Amount received

 

3,60,000

Buildings

1,60,000

 

Creditors

 

72,000

Bank Balance

95,000

 

Capital Account

 

5,00,000

Materials

2,00,000

 

Wages

1,80,000

 

Expenses

47,000

 

Plant

2,50,000

 

 

9,32,000

9,32,000

 

The work on Contract No.747 was commenced on 1st January, 2018. Materials costing Rs 1, 70,000 were sent to the site of the contract but those of Rs 6,000 were destroyed in an accident. Wages of Rs 1, 80,000 were paid during the year. Plant with a cost of Rs 2 lakhs was used from 1st January to 30th September and was then returned to the stores. Materials of the cost of Rs 4,000 were at site on 31st December, 2018.

 

The contract was for Rs 6, 00,000 and the contractee pays 75% of the work certified. Work certified was 80% of the total contract at the end of 2018. Uncertified work was estimated at Rs 15,000 on 31st December, 2018. Expenses are charged to the contract at 25% of wages. Plant is to be depreciated at 10% for the entire year.

 

You are required to prepare:

1.    Contract Account;

2.    Profit and Loss Account for the year ended 31st December, 2018; and

3.    Balance Sheet as at 31st December, 2018.

 

Solution: 4

                                                       Contract 747 Account

Particulars

Rs

Particulars

Rs

To D/Materials sent to site

1,70,000

By D/Materials at site

4,000

To D/Wages

1,80,000

By Abnormal loss of materials

6,000

To Expenses (1, 80,000 × 25%)

45,000

By Value of work certified [W.N. 2]

4,80,000

To Dep. on plant [W.N. 1]

20,000

By Cost of work not certified

15,000

To Notional Profit c/d

90,000

 

 

 

5,05,000

 

5,05,000

To P/L A/c [W.N. 4]

45,000

By Notional Profit b/d

90,000

To WIP Provision

45,000

 

 

 

90,000

 

90,000

 

                                        P/L A/c for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Abnormal loss of materials

6,000

By Profit from Contract A/c

45,000

To Dep. on plant [W.N. 1]

5,000

 

 

To Expenses (47,000 – 45,000)

2,000

 

 

To Net Profit (Transferred to B/S)

32,000

 

 

 

45,000

 

45,000

 

                                              Balance Sheet as at 31.12.2018

Liabilities

Rs

Rs

Assets

Rs

Rs

Capital:

 

 

Buildings

 

1,60,000

Opening balance

5,00,000

 

Plant

2,50,000

 

Add: Net Profit

32,000

5,32,000

Less: Depreciation

25,000

2,25,000

Creditors

 

72,000

Stock of Materials:

 

 

 

 

 

At Store

30,000

 

 

 

 

At Site

4,000

34,000

 

 

 

WIP      [W.N. 5]

4,50,000

 

 

 

 

Less: Cash received

3,60,000

90,000

 

 

 

Bank A/c

 

95,000

 

 

6,04,000

 

 

6,04,000

 

Working notes:

1.    Depreciation on plant

To be charged to Contract A/c:

 

 

 

For 1.1.2018 to 30.9.2018

2,50,000 × 10% × 9/12

Rs 18,750

         

For 1.10.2018 to 31.12.2018

50,000 × 10% × 3/12

Rs 1,250

Rs 20,000

To be charged to P/L A/c:

2,00,000 × 10% × 3/12

 

Rs 5,000

Total depreciation on plant

 

 

Rs 25,000

 

2.    Value of work certified

80% of Contract Price

80% of Rs 6, 00,000

Rs 4, 80,000

 

3.    Percentage Completion

= (Value of work certified ÷ Contract Price) × 100%

= (Rs 4, 80,000 ÷ Rs 6, 00,000) × 100%

= 80%

 

4.    Profit to be transferred to P/L A/c

= Notional Profit × (Cash Received ÷ Value of work certified) × 2/3

= Rs 90,000 × (Rs 3, 60,000 ÷ Rs 4, 80,000) × 2/3

= Rs 45,000

 

5.    Value of closing work-in-progress

     = Value of work certified + Cost of work not certified – WIP Provision

     = 4, 80,000 + 15,000 – 45,000

     = Rs 4, 50,000

 

 

Illustration: 5

The following Trial Balance was extracted on 31st December, 2018 from the books of Swastik Contractors Limited:

Particulars

Debit (Rs)

Credit (Rs)

Share Capital:

 

 

Shares of Rs 10 each

 

3,51,800

P&L A/c on 1.1. 2018

 

25,000

Provision for Dep. on Machinery

 

63,000

Cash received on account Contract - 7

 

12,80,000

Creditors

 

81,200

Land and Buildings (Cost)

74,000

 

Machinery (Cost)

52,000

 

Bank

45,000

 

Contract 7:

 

 

Materials

6,00,000

 

Direct Labour

8,30,000

 

Expenses

40,000

 

Machinery on site (Cost)

1,60,000

 

 

18,01,000

18,01,000

 

Contract 7 was begun on 1st January, 2018. The contract price is Rs 24, 00,000 and the customer has so far paid Rs 12, 80,000 being 80% of the work certified. The cost of the work done since certification is estimated at Rs 16,000. On 31st December, 2018, after the above Trial Balance was extracted machinery costing Rs 32,000 was returned to stores, and materials then on site were valued at Rs 27,000. Provision is to be made for outstanding direct labour amounting to Rs 6,000 and for depreciation of all machinery at 121/2 % on cost.

 

You are required to prepare:

(a) The Contract Account;

(b) The Profit and Loss Account for the year ended 31st December, 2018; and

(c) The Balance Sheet of Swastik Contractors Limited as at 31st December, 2018.

 

Solution: 5

                                                       Contract Account

Particulars

Rs

Particulars

Rs

To D/Materials sent to site

6,00,000

By D/Materials at site

27,000

To D/Labour (Incl. o/s 6,000)

8,36,000

By Value of work certified [W.N. 1]

16,00,000

To Expenses

40,000

By Cost of work not certified

16,000

To Dep. on machinery

    (1, 60,000 × 12.5%)

20,000

 

 

To Notional Profit c/d

1,47,000

 

 

 

16,43,000

 

16,43,000

To P/L A/c [W.N. 3]

78,400

By Notional Profit b/d

1,47,000

To WIP Provision

68,600

 

 

 

1,47,000

 

1,47,000

 

                                        P/L A/c for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Dep. on machinery

    (52,000 × 12.5%)

6,500

By Balance b/d

25,000

To Net Profit (Transferred to B/S)

96,900

By Profit from Contract A/c

78,400

 

1,03,400

 

1,03,400

 

                                              Balance Sheet as at 31.12.2018

Liabilities

Rs

Rs

Assets

Rs

Rs

Share Capital

 

3,51,800

Land and Buildings

 

74,000

P/L A/c balance

 

96,900

Machinery (at cost)

2,12,000

 

Creditors

 

81,200

Less: Depreciation

89,500

1,22,500

O/s Direct Labour

 

6,000

Stock of Materials

 

27,000

 

 

 

WIP      [W.N. 4]

15,47,400

 

 

 

 

Less: Cash received

12,80,000

2,67,400

 

 

 

Bank A/c

 

45,000

 

 

5,35,900

 

 

5,35,900

 

Working notes:

1.    Value of work certified

Cash received ÷ 80%

Rs 12, 80,000 ÷ 80%

Rs 16, 00,000

2.    Percentage Completion

= (Value of work certified ÷ Contract Price) × 100%

= (Rs 16, 00,000 ÷ Rs 24, 00,000) × 100%

= 66.67%

 

3.    Profit to be transferred to P/L A/c

= Notional Profit × (Cash Received ÷ Value of work certified) × 2/3

= Rs 1, 47,000 × (Rs 12, 80,000 ÷ Rs 16, 00,000) × 2/3

= Rs 78,400

 

4.    Value of closing work-in-progress

     = Value of work certified + Cost of work not certified – WIP Provision

     = 16, 00,000 + 16,000 – 68,600

     = Rs 15, 47,400

 



                                 Construction site


Illustration: 6

The following particulars are obtained from the books of ViCon Limited as on 31st March, 2018.

Plant and equipment at cost Rs 4, 90,000

Vehicles at cost Rs 2, 00,000

Details of contracts which remain uncompleted as on 31-3-2018 are as follows:    (Rs in lacs)

 

Contract nos.

Particulars

V.29

V.24

V.25

Estimated final sales value

8.00

5.60

16.00

Estimated total cost

6.40

7.00

12.00

Actual expenses incurred:

 

 

 

Wages

2.40

2.00

1.20

Materials

1.00

1.10

0.44

Overheads (excluding depreciation)

1.44

1.46

0.58

Total expenses (excluding dep.)

4.84

4.56

2.22

Value certified by architects

7.20

4.20

2.40

Progress payments received

5.00

3.20

2.00

 

Depreciation of plant and Equipment and Vehicle should be charged at 20% to the three contracts in proportion to work certified. You are required to prepare statements showing contract-wise and total –

a)    Profit / loss to be taken to the P & L A/c for the year ended 31st March, 2018, and

b)    Work-in-progress as would appear in the Balance Sheet as at 31-03-2018.

 

Solution: 6

                             Contract accounts               (Rs in lacs)

Particulars

V.29

V.24

V.25

Particulars

V.29

V.24

V.25

 

Rs

Rs

Rs

 

Rs

Rs

Rs

To D/Materials

1.00

1.10

0.44

 

 

 

 

To D/Wages

2.40

2.00

1.20

By Value of work

     Certified

7.20

4.20

2.40

To Overheads

    (Excl. Dep.)

1.44

1.46

0.58

 

 

 

 

To Depreciation

    [W.N. 1]

0.72

0.42

0.24

By P/L A/c (Loss

     Transferred)

 

0.78

0.06

To Notional profit

1.64

 

 

 

 

 

 

 

7.20

4.98

2.46

 

7.20

4.98

2.46

To P/L A/c [W.N. 3]

1.00

 

 

By Notional profit

1.64

 

 

To WIP Provision

0.64

 

 

 

 

 

 

 

1.64

 

 

 

1.64

 

 

Working notes:

1.    Amount of depreciation charged to contracts

Depreciation on plant and equipment

4,90,000 × 20%

 

Rs 98,000

Depreciation on vehicles

2,00,000 × 20%

 

Rs 40,000

Total depreciation

 

 

Rs 1,38,000

Charged to:

 

 

 

Contract V.29

1,38,000 × (7.20 ÷ 13.80)

Rs 72,000

Rs 0.72 lacs

Contract V.24

1,38,000 × (4.20 ÷ 13.80)

Rs 42,000

Rs 0.42 lacs

Contract V.25

1,38,000 × (2.40 ÷ 13.80)

Rs 24,000

Rs 0.24 lacs

 

2.    Profit to be transferred to P/L A/c (only for Contract V.29)

Estimated total profit   = Contract Price – Estimated Total Cost

                               = 8.00 – 6.40 = Rs 1.60 lacs

Profit to be transferred to P/L A/c

= Estimated Total Profit × (Cash Received ÷ Contract Price)

= 1.60 × (5.00 ÷ 8.00) = Rs 1.00 lacs

 

3.    Value of closing work-in-progress          (Rs in lacs)

 

V.29

V.24

V.25

Value of work certified

7.20

4.20

2.40

Add: Cost of work not certified

-

-

-

Less: WIP Provision

(0.64)

-

-

Value of closing work-in-progress

6.56

4.20

2.40

 

Illustration: 7

Deluxe Limited undertook a contract for Rs 5, 00,000 on 1.7.2018. On 30.6.2019, when the accounts were closed, the following details about the contract were gathered:

Particulars

Rs

Materials purchased

1,00,000

Wages paid

45,000

General expenses

10,000

Plant purchased

50,000

Materials on hand on 30.6.2011

25,000

Wages accrued on 30.6.2011

5,000

Work certified

2,00,000

Cash received

1,50,000

Work uncertified

15,000

Depreciation of plant

5,000

 

The above contract contained an escalation clause which read as follows:

“In the event of prices of materials and rates of wages increase by more than 5%, the contract price would be increased accordingly by 25% of the rise in the cost of materials and wages beyond 5% in each case.”

It was found that since the date of signing the agreement the prices of materials and rates of wages increased by 25%. The value of the work certified does not take into account the effect of the above clause.

Prepare the contract account. Workings should form part of the answer.

 

Solution: 7

Contract A/c of Deluxe Limited for the year ended 30.6.2019

Particulars

Rs

Particulars

Rs

To Materials purchased

1,00,000

By Materials on hand

25,000

To Wages paid             Rs 45,000

 

By Value of work certified

2,00,000

     ADD: Accrued           Rs 5,000

50,000

 

 

To General expenses

10,000

By Cost of work uncertified

15,000

To Plant depreciation

5,000

By Contract price escalation [W.N. 1]

5,000

To Notional Profit c/d

 80,000

 

 

 

2,45,000

 

2,45,000

To P/L a/c                  [W.N. 3]

19,512

By Notional Profit b/d

80,000

To WIP provision

60,488

 

 

 

80,000

 

80,000


Working notes:

1. Contract price escalation

(As per the Escalation Clause the contract price would be increased because prices of materials and rates of wages increased by 25%, which is more than the minimum required 5% increase in material prices and wage rates for the contract price to be increased.)

 

Particulars

Rs

Increase in material price [(Rs 1,00,000 – Rs 25,000) x (25/125)]

15,000

Increase in wages [(Rs 45,000 + Rs 5,000) x (25/125)]

10,000

Total increase (when material price and wages increased by 25%)

25,000

Total increase (when material price and wages increased by 5%)

5,000

Contract price escalation [25% of (Rs 25,000 – Rs 5,000)]                       

5,000

 

2. Percentage completion

     (Value of work certified ÷ Contract price) x 100

                   = (2, 05,000 ÷ 5, 05,000) x 100 = 40.60%

 

3. Profit to be transferred to profit and loss account

    Notional profit x (Cash received ÷ Value of work certified) x 1/3

                   = 80,000 x (1, 50,000 ÷ 2, 05,000) x 1/3

                   = Rs 19,512


Illustration: 8

M/s New Century Builders have entered into a contract to build an office building complex for Rs 480 lakh. The work started on 1st April, 2018 and it is estimated that the contract will take 15 months to be completed. Work has progressed as per schedule, and the actual costs charged till 31st March, 2019 are as follows:

Particulars

Rs (in lacs)

Materials

112.20

Labour

162.00

Hire charges for equipments

36.00

Establishment charges

32.40

Total

342.60

 

The following information is available:

Particulars

Rs (in lacs)

Materials in hand as on 31st March, 2019

6.60

Work certified as on 31st March, 2019

400.00

On account payment received till 31st March, 2019

324.00

Work not yet certified as on 31st March, 2019

7.50

 

As per management estimates, the following further expenditure will be incurred to complete the work:

Particulars

Rs (in lacs)

Materials

10.50

Labour

16.00

Sub-contractors

20.00

Hire charges for equipments

3.00

Establishment charges

6.90

 

You are required to compute the value of work-in-progress as on 31st March, 2019 after considering a reasonable margin of profit and to show the appropriate accounts. Make a provision for contingencies amounting to 5% of the total costs after charging such provision.

 

Solution: 8

                          Contract account      (Rs in lacs)

Particulars

Rs

Particulars

Rs

To Materials

112.20

By Materials in hand

6.60

To Labour

162.00

By Cost of work not certified

7.50

To Hire charges for equipments

36.00

By Value of work certified

400.00

To Establishment charges

32.40

 

 

To Notional  profit c/d

71.50

 

 

 

414.10

 

414.10

To P/L a/c       [W.N. 2]

40.50

By Notional profit b/d

71.50

To WIP provision

31.00

 

 

 

71.50

 

71.50

Working notes:

1. Estimated total profit:            (Rs in lacs)

Particulars

Rs

Rs

Total cost up-to-date:

 

 

Materials (112.20 – 6.60)

105.60

 

Labour

162.00

 

Hire charges for equipment

36.00

 

Establishment charges

32.40

336.00

Add: Estimated further cost:

 

 

Materials (6.60 + 10.50)

17.10

 

Labour

16.00

 

Sub-contractors

20.00

 

Hire charges for equipment

3.00

 

Establishment charges

6.90

63.00

Estimated total cost excluding provision

 

399.00

Add: Provision for contingencies: (399.00 x 5 ÷ 95)

 

21.00

Estimated total cost including provision

 

420.00

Contract price

 

480.00

Estimated total profit

 

60.00

 

2. Profit to be transferred to profit and loss account:

     Estimated total profit x (Cash received ÷ Contract price)

     = 60.00 x (324.00 ÷ 480.00) = Rs 40.50 Lakh

 

3. Value of work-in-progress (WIP):

     Value of work certified + Cost of work not certified − WIP Provision

     = 400.00 + 7.50 − 31.00 = Rs 376.50 Lakh

 

Illustration: 9

United Construction Company got a contract in January, 2018 for construction of a bridge. The contract price was Rs 5, 00,000. The Company incurred the following expenses up to 31st December, 2018:

Particulars

Rs

Materials issued

1,10,000

Wages

40,000

Direct expenses

20,000

Plant purchased on 30th June, 2018

1,00,000

Materials in hand

5,000

Cost of uncertified work

2,000

 

Depreciation is to be charged on plant @ 10% per annum. Other works expenses are to be charged    @ 20% of wages and office expenses are to be charged @ 10% of works cost. The value of work certified by the engineer up to 31st December, 2018 was Rs 3, 00,000 retention money being 20% of the certified value.

 

Prepare a Contract Account showing therein the amount of profit or loss to be transferred to profit and loss account.

 

Solution: 9

                                                      Contract account for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Materials

1,10,000

By Materials in hand

5,000

To Labour

40,000

By Cost of work not certified

2,000

To Direct expenses

20,000

By Value of work certified

3,00,000

To Depreciation on plant

    (1,00,000 x 10% x 6/12)

 

5,000

 

 

To Other works expenses

    [40,000 x 20%]

 

8,000

 

 

To Office expenses

    [{(1,10,000 – 5,000)

     +40,000+20,000+5,000

     +8,000} x 10%]

 

 

 

17,800

 

 

To Notional profit c/d

1,06,200

 

 

 

3,07,000

 

3,07,000

To P/L a/c      [W.N. 2]

56,640

By Notional profit b/d

1,06,200

To WIP provision (b/f)

49,560

 

 

 

1,06,200

 

1,06,200

 

Working notes:

1. Percentage completion:

     (Value of work certified ÷ Contract price) x 100

     = (3, 00,000 ÷ 5, 00,000) x 100 = 60%

 

2. Profit to be transferred to profit and loss account:

     Notional profit x (Cash received ÷ Value of work certified) x 2/3

     = 1, 06,200 x (2, 40,000 ÷ 3, 00,000) x 2/3 = Rs 56,640

 

Illustration: 10

MK Construction Ltd. entered into a contract to construct a building. The contract value is Rs 6, 50,000 to be realised in instalments on the basis of the value of work certified by the architect subject to retention of 10%. The work commenced on 1.4.2018 but it remained incomplete on 31.12.2018 when the final accounts are to be prepared. The facts and figures of the contract are:

 

Particulars

Rs

Plant charged to contract at the commencement

32,000

Materials charged to contract

1,80,000

Wages paid

87,000

Expenses incurred on the contract

38,750

 

Total establishment expenses amounted to Rs 41,000 out of which 25% is attributable to this contract. Out of the materials issued to the contract, materials costing Rs 4,000 were sold for Rs 5,000. A part of the plant (costing Rs 2,000) was damaged on 1.10.2018 and the scrap realised Rs 300 only. Plant, costing Rs 3,000, was transferred to another contract site on 31.12.2018. Plant is to be depreciated @ 10% p.a.

Other information is:

 

Particulars

Rs

Materials in hand on 31.12.2010

17,500

Cash received from the contractee

3,06,000

Cost of work yet to be certified

30,000

 

Prepare a Contract Account showing therein the amount of profit or loss to be transferred to profit and loss account and compute the value of work-in-progress as on 31.12.2018.

 

Solution: 10

Contract account

Particulars

Rs

Particulars

Rs

To Materials

1,80,000

By Sale of materials at site

5,000

To Labour

87,000

By Closing materials at site

17,500

To Direct expenses

38,750

By Profit and loss A/c (abnormal

    loss due to plant damaged)

    Cost of plant               2,000

    (−) Depreciation            100

    [2,000 x 10/100 x 6/12]

    (−) Scrap realised          300

 

 

 

 

 

1,600

To Plant sent to site

32,000

By Sale of scrap of plant

300

To Establishment expenses

10,250

By Plant transferred to other site

    Cost of plat                 3,000

    (−) Depreciation             225

    [3,000 x 10/100 x 9/12]

 

 

 

2,775

To Profit and loss A/c

    (profit on sale of

    materials)

 

1,000

By Plant at site

    Cost of plat                27,000

    (−)Depreciation           2,025

    [27,000 x 10/100 x 9/12]

 

 

 

24,975

 

 

By Cost of work not certified

30,000

To Notional Profit c/d

73,150

By Value of work certified

    [3,06,000 x 100/90]

 

3,40,000

 

4,22,150

 

4,22,150

To P/L a/c     [W.N. 2]

43,890

By Notional Profit b/d

73,150

To WIP provision

29,260

 

 

 

73,150

 

73,150

 

Working notes:

1. Percentage completion:

     (Value of work certified ÷ Contract price) x 100

     = (3, 40,000 ÷ 6, 50,000) x 100 = 52.3%

2. Profit to be transferred to profit and loss account:

     Notional profit x (Cash received ÷ Value of work certified) x 2/3

     = 73,150 × (3, 06,000 ÷ 3, 40,000) × 2/3 = Rs 43,890

3. Value of work-in-progress (WIP):

     Value of work certified + Cost of work not certified − WIP Provision

     = 3, 40,000 + 30,000 − 29,260 = Rs 3, 40,740

 



                                    Construction site


Illustration: 11

Nilcom Construction Company commenced a contract on 1.7.2018. The contract price is Rs 9, 00,000. Actual expenditure till 31.12.2018 and estimated expenditure in 2019 are given below:

Particulars

Actual till 31.12.18   (Rs)

Estimated for 2019  (Rs)

Purchase of materials

1,50,000

2,60,000

Labour

1,10,000

1,20,000

Purchase of plant (original cost)

80,000

Miscellaneous expenses

40,000

71,000

 

As at 31.12.18    (Rs)

As at 30.9.19    (Rs)

Return of plant to stores (original cost)

20,000

50,000

Materials at site

10,000

Nil

Work certified

4,00,000

Full

Work uncertified

15,000

Nil

Cash received

3,60,000

Full

 

Depreciation is charged on plant @ 20% p.a. on original cost (calculation to be made on time basis). The contract is likely to be completed by 30.9.2019.

 

You are required to prepare the contract account for the year ended 31.12.2018. It has been decided to estimate the total profit on the contract and to take to the credit of profit and loss account that proportion of estimated profit on realised basis which the work actually certified bears to the total contract.

 

Solution: 11

Contract account of Nilcom Construction Company

For the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Materials purchased

1,50,000

By Materials at site

10,000

To Labour

1,10,000

By Plant at site

    (depreciated value)

54,000

To Plant purchased

80,000

By Plant returned to store

    (depreciated value)

18,000

To Miscellaneous expenses

40,000

By Cost of work uncertified

15,000

To Notional profit c/d

 1,17,000

By Value of work certified

4,00,000

 

4,97,000

 

4,97,000

To P/L A/c             [W.N. 6]

52,800

By Notional profit b/d

1,17,000

To WIP provision

64,200

 

 

 

1,17,000

 

1,17,000


Working notes:

Sl. No.

Particulars

Rs

1

Plant returned to store on 31.12.2018:

 

 

Original cost

20,000

 

LESS: Depreciation for 6 months @ 20%

2,000

 

 

18,000

2

Plant at site on 31.12.2018:

 

 

Original cost (Rs 80,000 – 20,000)

60,000

 

LESS: Depreciation for 6 months @ 20%

6,000

 

 

54,000

3

Plant returned to store on 30.9.2019:

 

 

Original cost

50,000

 

LESS: Depreciation for 15 months @ 20%

12,500

 

 

37,500

4

Plant at site on 30.9.2019:

 

 

Original cost (Rs 80,000 − 20,000 − 50,000)

10,000

 

LESS: Depreciation for 15 months @ 20%

2,500

 

 

7,500

 

5. Estimated total profit:

Particulars

Rs

Rs

Total cost up-to-date:

 

 

Materials (1,50,000 – 10,000)

1,40,000

 

Labour

1,10,000

 

Plant (80,000 – 54,000 – 18,000)

[Alternative calculation: Rs 80,000 × 20% × 6/12]

8,000

 

Miscellaneous expenses

40,000

2,98,000

Add: Estimated further cost:

 

 

Materials (10,000 + 2,60,000)

2,70,000

 

Labour

1,20,000

 

Plant (54,000 – 7,500 – 37,500)

[Alternative calculation: Rs 60,000 × 20% × 9/12]

9,000

 

Miscellaneous expenses

71,000

4,70,000

Estimated total cost

 

7,68,000

Contract price

 

9,00,000

Estimated total profit

 

1,32,000

 

6. Profit to be transferred to profit and loss account:

     Estimated total profit x (Cash received ÷ Contract price)

     = 1, 32,000 x (3, 60,000 ÷ 9, 00,000) = Rs 52,800

 

Illustration: 12

On 1.4.2018 Bill Ltd. commenced work on a contract which was to be completed by 30.6.2019 at an agreed price of Rs 5, 20,000. From the following information you are required to prepare the Contract Account for the year ended 31.12.2018 and show the calculation of the sum to be credited to the profit and loss account for that year.

Bill Ltd.’s financial year ended on 31.12.2018, and on that day expenditure on the contract totalled Rs 2, 63,000 made up as follows:

Particulars

Rs

Plant

30,000

Materials

1,24,000

Wages

95,000

Sundry expenses

5,000

Head Office charges

9,000

Total

2,63,000

 

Cash totalling Rs 1, 95,000 had been received by 31.12.2018 representing 75% of the work certified till that date. Cost of work completed but not certified till that date was Rs 30,000. A sum of Rs 9,000 had been obtained from the sale of some unsuitable materials which had cost of Rs 8,000. On 31.12.2018 stocks of unused materials on site had cost of Rs 10,000 and the plant was valued at Rs 20,000.

To complete the contract by 30.6.2019 it was estimated that −

(a)      The following additional expenditure would be incurred:

 

Particulars

Rs

Wages

64,000

Materials

74,400

Sundry expenses

9,000

 

(b)   Further plant costing Rs 25,000 would be required;

(c)   The residual value of all plant as at 30.6.2019 would be Rs 15,000;

(d)   Head office charges to the contract would be at the same annual rate plus 10%.

 

It was estimated that the contract would be completed on time, but that a contingency provision of Rs 15,000 should be made. From this estimate and the expenditure already incurred, it was decided to estimate the total profit that would be made on the contract and to take to the credit of the profit and loss account for the year ended 31.12.2018, that proportion of the total profit as it relates to the work actually certified to that date.

 

Solution: 12

Contract A/c of Bill Limited for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Plant

30,000

By Materials at site

10,000

To Materials

1,24,000

By Plant at site (depreciated value)

20,000

To Wages

95,000

By Bank (sale of materials)

9,000

To Sundry expenses

5,000

By Cost of work uncertified

30,000

To Profit and loss account

    (profit on sale of materials)

1,000

By Value of work certified

    [(1,95,000 x (100 ÷ 75)]

2,60,000

To Head office charges

9,000

 

 

To Notional Profit

 65,000

 

 

 

3,29,000

 

3,29,000

To P/L a/c          [W.N. 2]

32,250

By Notional Profit

65,000

To WIP provision

32,750

 

 

 

65,000

 

65,000

 

Working notes:

1. Estimated total profit:

Particulars

Rs

Rs

Total costs incurred up to 31.12.2018:

 

 

Plant (30,000 – 20,000)

10,000

 

Materials (1,24,000 – 8,000 – 10,000)

1,06,000

 

Wages

95,000

 

Sundry expenses

5,000

 

Head office charges

9,000

2,25,000

Add: Estimated further cost:

 

 

Plant (20,000 + 25,000 – 15,000)

30,000

 

Materials (10,000 + 74,400)

84,400

 

Wages

64,000

 

Sundry expenses

9,000

 

Head office charges [{(9,000 ÷ 9) x 6} x 1.10]

6,600

1,94,000

 

 

4,19,000

Add: Provision for contingencies:

 

15,000

Estimated total cost

 

4,34,000

Contract price

 

5,20,000

Estimated total profit

 

86,000

 

2. Profit to be transferred to profit and loss account:

     Estimated total profit x (Cash received ÷ Contract price)

     = 86,000 x (1, 95,000 ÷ 5, 20,000) = Rs 32,250

 

Illustration: 13

Deluxe Limited undertook a contract for Rs 5, 00,000 on 1st January, 2018. The company furnishes the following details for the year ended 31st December, 2018:

Particulars

Rs

Materials consumed

1,65,000

Direct expenses

5,000

Wages

30,000

Materials returned to stores

5,000

Materials stolen from site

10,000

Insurance claim admitted

6,000

Other works expenses @ 20% on wages.

 

Office expenses @ 10% on works cost.

 

Materials in hand on 31st December, 2018

15,000

Cash received to the extent of 90% of works certified

2,70,000

Cost of works uncertified

11,000

 

Plant sent to site cost Rs 60,000 with a scrap value of Rs 10,000 and a useful life of 5 years. The plant was used in the contract for 146 days.

Prepare contract account showing therein the cost of materials issued to the site and the amount of profit or loss to be transferred to the profit and loss account. Show also the value of work-in-progress separately.

Solution: 13

Contract A/c of Deluxe Ltd. for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Materials issued to site [W.N. 1]

1,95,000

By Materials stolen               10,000

 

 

 

Less: Ins. Claims admitted      6,000

4,000

To Wages

30,000

By Insurance claim admitted

6,000

To Direct expenses

5,000

By Materials returned to store

5,000

To Depreciation on plant [W.N. 2]

4,000

By Materials in hand at site

15,000

To Other works expenses

    [30,000 x 20%]

 

6,000

By Cost of works uncertified

11,000

To Office expenses [W.N. 3]

21,000

By Value of works certified [W.N. 4]

3,00,000

To Notional profit c/d

80,000

 

 

 

3,41,000

 

3,41,000

To P/L A/c             [W.N. 6]

48,000

By Notional profit b/d

80,000

To WIP provision [b/f]

32,000

 

 

 

80,000

 

80,000


Working notes:

1.    Materials issued to site:

 

Rs

Materials consumed

1,65,000

Add: Materials returned

5,000

Add: Materials stolen

10,000

Add: Materials in hand at site

15,000

 

1,95,000

 

2.    Depreciation on plant:

Depreciation per annum

(Rs 60,000 – 10,000) ÷ 5 = Rs 10,000

Depreciation for the accounting period

(Rs 10,000 ÷ 365) × 146 = Rs 4,000

 

3.    Office expenses:

 

Rs

Materials consumed

1,65,000

Add: Direct wages

30,000

Add: Direct expenses

5,000

Add: Depreciation on plant

4,000

Add: Other works expenses

6,000

Works cost

2,10,000

Office expenses [10% of works cost]

21,000

 

4.    Value of work certified:

Cash received

Rs 2,70,000

Value of work certified

Rs 2,70,000 × 100/90 = Rs 3,00,000

 

5.    Percentage completion:

     (Value of work certified ÷ Contract price) x 100

     = (3, 00,000 ÷ 5, 00,000) x 100 = 60%

 

6.    Profit to be transferred to profit and loss account:

     Notional profit x (Cash received ÷ Value of work certified) x 2/3

     = 80,000 x (2, 70,000 ÷ 3, 00,000) x 2/3 = Rs 48,000

 

Illustration: 14

Modern Construction Company, with a paid up share capital of Rs 50 lakhs undertook a contract for constructing LIG Houses. The contract price was Rs 50 lakhs and the work commenced on 1-1-2018. Cash received on account of contract on 31-12-2018 was Rs 18 lakhs (90% of the work was certified). Work completed but not certified was estimated at Rs 1, 00,000. As on 31-12-2018 material at site was estimated at Rs 30,000 and machinery costing Rs 2, 00,000 was returned to store. Plant and machinery are to be depreciated at 5% on original cost. Wages outstanding on 31-12-2018 was Rs 5,000.

 

The following were the ledger balances (Dr.) as per the Trial Balance as on 31-12-2018:

 

Ledger Accounts

Balances (Rs)

Land and building

15,00,000

Plant and machinery at cost (60% at site)

25,00,000

Lorries and other vehicles

8,00,000

Furniture

50,000

Materials sent to site

14,00,000

Other equipments

10,000

Fuel and power

1,25,000

Site expenses

5,000

Postage and telegram

4,000

Office expenses

8,000

Rent and rates

15,000

Cash at bank

1,33,000

Wages

2,50,000

 

Prepare:

1.  Contract account for the year ended 31-12-2018,

2.  Profit and loss account for the year ended 31-12-2018, and

3.  Balance sheet as at 31-12-2018.

 

Solution: 14

Contract A/c of Modern Construction Company

For the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Materials sent to site

14,00,000

By Materials at site

30,000

To Wages (Including o/s wages)

2,55,000

By Value of work certified [W.N.2]

20,00,000

To Site expenses

5,000

By Cost of work not certified

1,00,000

To Dep. on P/M [WN: 1]

85,000

 

 

To Fuel and power

1,25,000

 

 

To Notional profit c/d

2,60,000

 

 

 

21,30,000

 

21,30,000

To P/L a/c       [W.N. 4]

78,000

By Notional profit b/d

2,60,000

To WIP provision (bal. figure)

1,82,000

 

 

 

2,60,000

 

2,60,000

 

Profit and loss account for the year ended 31.12.2018

Particulars

Rs

Particulars

Rs

To Postage and telegram

4,000

By Contract A/c (proportion of

    Notional Profit)

78,000

To Office expenses

8,000

 

 

To Dep. on P/M [WN: 1]

40,000

 

 

To Rent and rates

15,000

 

 

To Net profit (transferred

     to balance sheet)

11,000

 

 

 

78,000

 

78,000

 

Balance sheet as on 31.12.2018

Liabilities

Rs

Assets

Rs

Share capital

50,00,000

P/M at cost                    25,00,000

 

Net profit

11,000

Less: Depreciation          (1,25,000)

23,75,000

Outstanding wages

5,000

Land and building

15,00,000

 

 

Lorries and other vehicles

8,00,000

 

 

Furniture

50,000

 

 

Other equipments

10,000

 

 

Stock of materials

30,000

 

 

Work-in-progress [W.N. 5]  19,18,000

 

 

 

Less: Cash received          (18,00,000)

1,18,000

 

 

Cash at bank

1,33,000

 

50,16,000

 

50,16,000

 

Working notes:

1.    Depreciation on plant and machinery:

Particulars

Rs

Plant and machinery at site on 31-12-2018 (at cost)

[60% of 25,00,000]

 

15,00,000

ADD: Plant and machinery returned to store from site

        on 31-12-2018 (at cost)

 

2,00,000

Plant and machinery used in the contract during 2018 (at cost)

17,00,000

Depreciation on plant and machinery charged to contract

[5% of 17,00,000]                                                                    (A)

 

85,000

Depreciation on plant and machinery directly charged to P/L A/c

[5% of (25,00,000 – 17,00,000)]                                                (B)

 

40,000

Total depreciation on plant and machinery                               [A + B]

1,25,000

 

2.    Value of work certified:

Cash received

Rs 18,00,000

Value of work certified

Rs 18,00,000 × 100/90 = Rs 20,00,000

 

3.    Percentage completion:

     (Value of work certified ÷ Contract price) x 100%

     = (20, 00,000 ÷ 50, 00,000) x 100% = 40%

 

4.    Profit to be transferred to profit and loss account:

     Notional profit x (Cash received ÷ Value of work certified) x 1/3

     = 2, 60,000 x (18, 00,000 ÷ 20, 00,000) x 1/3

     = Rs 78,000

 

5.    Work-in-progress:

= Value of work certified + Cost of work not certified – WIP Provision

= 20, 00,000 + 1, 00,000 – 1, 82,000 = Rs 19, 18,000


Illustration: 15

Reliable Construction Limited commenced a contract on 1st April, 2018. The total contract was for        Rs 49, 21,875. It was decided to estimate the total profit on the contract and to take to the credit of profit and loss account that proportion of estimated profit on cash basis which work completed bore to total contract. Actual expenditure for the period 1st April, 2018 to 31st March, 2019 and estimated expenditure for the period 1st April, 2019 to 30th September, 2019 are given below:

Particulars

1.4.2018 to

31.3.2019

Actuals (Rs)

1.4.2019 to

30.9.2019

Estimated (Rs)

Materials issued

7,76,250

12,99,375

Labour:

 

 

Paid

5,17,500

6,18,750

Prepaid

37,500

Outstanding

12,500

5,750

Plant purchased

4,00,000

Expenses:

 

 

Paid

2,25,000

3,75,000

Outstanding

25,000

10,000

Prepaid

15,000

Plant returns to store

(historical cost)

1,00,000

(on 30.9.2018)

3,00,000

(on 30.9.2019)

Work certified

22,50,000

Full

Work uncertified

25,000

Cash received

18,75,000

Materials at site

82,500

42,500

 

The plant is subject to annual depreciation @ 25% on written down value method. The contract is likely to be completed on 30th September, 2019.

 

Required: Prepare the contract account and determine the profit on the contract for the year ending on 31st March, 2019 on prudent basis, which has to be credited to profit and loss account.

 

Solution: 15

Contract A/c of Reliable Construction Limited for the year ended 31.3.2019

Particulars

Rs

Rs

Particulars

Rs

Rs

To Materials issued

 

7,76,250

By Plant (Returned):

 

 

To Wages

5,17,500

 

    Cost

1,00,000

 

    Add: Outstanding

12,500

 

    Less: Depreciation

(12,500)

87,500

    Less: Prepaid

(37,500)

4,92,500

By Materials at site

 

82,500

To Plant purchased

 

4,00,000

By Plant at site:

 

 

To Expenses

2,25,000

 

    Cost

3,00,000

 

    Add: Outstanding

25,000

 

    Less: Depreciation

(75,000)

2,25,000

    Less: Prepaid

(15,000)

2,35,000

By Value of work

    Certified

 

22,50,000

To Notional Profit c/d

 

7,66,250

By Cost of work

    Uncertified

 

25,000

 

 

26,70,000

 

 

26,70,000

To P/L A/c

[W.N. 1, 2]

 

3,89,000

By Notional Profit b/d

 

7,66,250

To WIP Provision (b/f)

 

3,77,250

 

 

 

 

 

7,66,250

 

 

7,66,250

 

Working notes:

1. Estimated total profit:

Particulars

Rs

Rs

Total costs incurred up to 31.3.2019:

 

 

Plant (12,500 + 75,000)

87,500

 

Materials (7,76,250 – 82,500)

6,93,750

 

Wages

4,92,500

 

Expenses

2,35,000

15,08,750

Add: Estimated further cost:

 

 

Plant [(3,00,000 – 75,000) × 25% × 6/12]

28,125

 

Materials (82,500 + 12,99,375 – 42,500)

13,39,375

 

Wages (6,18,750 + 37,500 – 12,500 + 5,750)

6,49,500

 

Expenses (3,75,000 + 15,000 – 25,000 + 10,000)

3,75,000

23,92,000

Estimated total cost

 

39,00,750

Contract price

 

49,21,875

Estimated total profit

 

10,21,125

 

2. Profit to be transferred to profit and loss account:

     Estimated total profit x (Cash received ÷ Contract price)

     = 10, 21,125 x (18, 75,000 ÷ 49, 21,875) = Rs 3, 89,000


Click here for Illustration: 16 and

Solution in PDF


6 comments:

  1. I read this airticle and understood this airticle. This airticle is very easy to understand for student. My suggestion to follow this airtle.

    ReplyDelete
  2. Thank you Subhadip for your comments. I assure you of publishing more such students-friendly quality articles on different topics of various subjects of CMA and other professional courses.

    ReplyDelete
  3. I read this article thoroughly and i understood each and everything. It was very informative which hepled me alot in my preparation for my last examinations. I would like to have more such sort of aticles with same quality from this blog. Further i also want my friends to follow this blog for good quality preparations for their future exams. :)

    ReplyDelete
  4. I like this article and it helped me a lot.

    ReplyDelete
  5. This article is easy to understand and helpful.

    ReplyDelete