Cost Accounting
CONTRACT COSTING
Part A: Discussion of basic theories including Tables, Formats and different Formulas
Part B: 16 Illustrations with Solutions
Part A
Construction site
Introduction
Contract Costing or Terminal Costing as it is often
termed, is a variant of the job costing system, which is applied in businesses
engaged in building or other construction work. The jobs are usually the
contracts entered into with the customers. As the number of such contracts
handled at a time by a business may not be usually large, Contract Costing is
comparatively simpler in operation than job costing system. The basic
principles applied in Contract Costing are the same as those used in job
costing except that these are modified to suit the particular requirements of
the contracts.
Contract Costing is a type of costing used in
construction activities such as construction of buildings, roads, bridges etc.
The person who takes contract for a price is called the Contractor and
the person from whom it is taken is called the Contractee. We are mainly concerned with the books of the
contractor. To find out profit earned or loss incurred on the contract, the
contractor prepares a nominal account in his books called ‘Contract Account’.
In this account, all the expenses incurred by the contractor are debited and
the income i.e. mainly work certified is credited; the difference represents
profit or loss.
The items generally debited are materials, wages,
establishment expenses & other expenses. Depreciation of assets used in the
contract will also be debited, but unlike in other types of accounts it is
customary in Contract Accounts to debit the opening balance of the assets and
credit the closing balance of the same instead of depreciation, wherever it is
convenient to do so. Amounts credited are work-in-progress, which consists of
value of work certified and cost of work not certified and any scrap of materials
etc.
The contracts usually run for a number of years;
however it is necessary to find out the profit or loss at the end of every
year. The profit earned on a Contract Account is primarily called Accounting Profit
or Notional
Profit. A portion of the Notional Profit is kept as
work-in-progress provision and the other portion is transferred to Profit &
Loss Account. The profit to be transferred to Profit & Loss Account out of
the Notional Profit is ascertained by taking into consideration the degree of
completion of the work, cash received etc.
Click here for "Format of Contract Account" in PDF
Profit to be transferred to Profit and Loss Account
If there is any contract which is incomplete at the
end of the financial year, profit on such incomplete contract is also
considered for the purpose of profit and loss account subject to some
restrictions. Usually, only a part of such profit on incomplete contract is
transferred to profit and loss account. But if there is a loss on incomplete
contract, the whole of the loss is debited to profit and loss account.
The guidelines in this regard are as follows:
1. If the contract
is completed 25% or less no profit is transferred to profit and loss account.
2. If the contract
is completed above 25% but below 50%, profit to be transferred to profit and
loss account is –
Notional profit x (Cash received ÷
Value of work certified) x 1/3 |
3. If the contract
is completed 50% or more but less than 90%, profit to be transferred to profit
and loss account is –
Notional profit x (Cash received ÷ Value of work certified) x 2/3 |
4. If the contract
is almost completed (i.e. 90% or more), profit to be transferred to profit and
loss account should be calculated on the basis of
estimated total profit in any of the following two ways:
First alternative (if not specifically instructed to follow
the second alternative)
Profit to be transferred to profit and loss account = Estimated total profit x (Cash received ÷ Contract price) |
Second alternative (to be applied only when there is
specific instruction)
Profit to be transferred to profit and loss account = Estimated total profit x (Value of work certified ÷ Contract price) |
Here, Estimated Total Profit |
= Contract price – Estimated total
cost of completion of the contract |
= Contract price − (Total cost
up-to-date + Estimated further cost) |
Important Notes:
1.
Percentage completion = |
(Value of work certified ÷ Contract price) x 100 |
2. Balance of the Accounting / Notional Profit,
after proportionate profit is transferred to P/L A/c, will be transferred to WIP
Provision Account.
3. If there is a notional loss on incomplete contract, the
whole of the loss is transferred to profit and loss account.
4. If in any
problem estimated further cost to complete the contract is given, profit to be transferred
to profit and loss account should be calculated on the basis of estimated total
profit only. In such cases percentage completion of the contract
has to be ignored. In other words, even if the percentage completion of the
contract is less than 90%, if the estimated further cost to complete the
contract is given in the problem, profit to be transferred to profit and loss account
should be calculated on the basis of estimated total profit.
5. When the completion of contract is 90% or more,
but the estimated further cost to complete the contract is not given in the
problem, profit to be taken to profit and loss account should be calculated by
using the following formula:
Profit to be transferred to profit and loss account = |
Notional profit x (Value of work certified ÷ Contract price) |
Work-in-Progress (WIP)
Work-in-progress can be calculated by using any of the
following two formulas:
1 |
WIP = |
|
Cost of work done + Profit transferred to profit and loss account |
2 |
WIP = |
|
Value of work certified + Cost of work not certified – WIP Provision |
Construction site
Part B
Contract Costing
Selected Problems
Illustration:
1
A contractor commenced the work on a particular
contract on 1st April, 2018 and he usually closes his books of
accounts on 31st December of each year. The following information is
revealed from his costing records on 31st December, 2018.
|
Rs |
Materials sent to site |
43,000 |
Jr. Engineer |
12,620 |
Labour |
1,00,220 |
A machine costing Rs 30,000 remained in use on site for 1/5th of year. Its working life was estimated at 5 years and scrap value at Rs 2,000. A supervisor is paid Rs 2,000 per month and had devoted half of his time on the contract. All other expenses were Rs 14,000 and the materials on site were Rs 2,500.
The contract price was Rs 4, 00,000. On 31st December, 2018 2/3rd of the contracts were completed. However, the architect gave certificate only for Rs 2, 00,000 on which 80% was paid.
Prepare Contract
Account.
Solution: 1
Contract account
Particulars |
Rs |
Particulars |
Rs |
To
D/Materials sent to site |
43,000 |
By
D/Materials at site |
2,500 |
To
D/Labour |
1,00,220 |
By Value of work certified |
2,00,000 |
To
Dep. on machinery [(30,000 – 2,000) × 1/5
× 1/5] |
1,120 |
By
Cost of work not certified [W.N. 1] |
44,365 |
To
Jr. Engineer |
12,620 |
|
|
To
Supervisor [2,000 × 9 × ½ ] |
9,000 |
|
|
To
Other expenses |
14,000 |
|
|
To
Notional Profit c/d |
66,905 |
|
|
|
2,46,865 |
|
2,46,865 |
To
P/L a/c [W.N. 3] |
35,683 |
By
Notional Profit b/d |
66,905 |
To
WIP Provision (b/f) |
31,222 |
|
|
|
66,905 |
|
66,905 |
Working notes:
1. Computation of cost of work not certified
|
Rs |
Total cost incurred up to 31.12.2018 |
1,77,460 |
Proportion of total contract completed up to
31.12.2018 |
2/3 |
∴ Estimated total cost to complete the contract (1,77,460 × 3/2) |
2,66,190 |
Proportion of total contract certified up to
31.12.2018 |
½ |
⇒ Proportion of estimated total cost certified up to
31.12.2018 |
½ |
⇒ Cost of work certified (2,66,190 × ½ ) |
1,33,095 |
⇒ Cost of work not certified (1,77,460 – 1,33,095) |
44,365 |
2. Percentage Completion
= (Value of work certified ÷ Contract Price) × 100%
= (Rs 2, 00,000 ÷ Rs 4, 00,000) × 100%
= 50%
3. Profit to be transferred to P/L A/c
= Notional Profit × (Cash Received ÷ Value of work
certified) × 2/3
= Rs 66,905 × (Rs 1, 60,000 ÷ Rs 2, 00,000) × 2/3
= Rs 35,683
Illustration: 2
The following figures are supplied to you by a contractor for the year
ending 31st December, 2018:
Particulars |
Rs |
Work-in-Progress
on 31-12-2017
Rs 85,000 |
|
Less:
Cash received from contractee
(Rs 55,000) |
30,000 |
During
the year: |
|
Wages |
8,500
|
Materials
bought |
6,000
|
Working
expenses |
1,500
|
Materials
issued from stores |
10,500
|
Administrative
expenses ( Rs 250
are chargeable to P and L A/c ) |
1,250
|
Plant |
2,500
|
Material
returned to supplier |
450
|
Material
returned to stores |
550
|
Work
certified |
15,000
|
Contracts
finished (Work certified and handed over to contractee) |
22,500
|
Profits
taken upon contracts |
11,500
|
Advances
from contractee |
40,000
|
Prepare the Contract Account and the Contractee’s, and
show the work-in-progress as it would appear in the Balance sheet.
Solution: 2
Contract account
Particulars |
Rs |
Particulars |
Rs |
To
Opening WIP |
85,000 |
By
Materials returned (450 + 550) |
1,000 |
To
D/Materials (6,000 + 10,500) |
16,500 |
By Value of work certified |
15,000 |
To
D/Wages |
8,500 |
By
Contractee A/c |
22,500 |
To
Working expenses |
1,500 |
By Cost of work not certified (b/f) |
88,000 |
To
Administrative expenses |
1,000 |
|
|
To
Plant (Depreciation) |
2,500 |
|
|
To
P/L A/c |
11,500 |
|
|
|
1,26,500 |
|
1,26,500 |
Contractee account
Particulars |
Rs |
Particulars |
Rs |
To Contract A/c |
22,500 |
By
Balance b/d |
55,000 |
To Balance c/d (Balance of cash received as advance) |
72,500 |
By Cash |
40,000 |
|
95,000 |
|
95,000 |
Balance Sheet as
at................ (Extract)
Liabilities |
Rs |
Assets |
Rs |
|
|
Closing
WIP (W.N.) 1,03,000 |
|
|
|
Less: Cash received 72,500 (as advance) |
30,500 |
|
|
|
|
Working notes:
Value
of closing work-in-progress
= Value of work certified + Cost of work not certified
– WIP Provision
= 15,000 + 88,000 – Nil
= Rs 1, 03,000
Illustration:
3
A firm of engineers undertook three contracts
beginning on 1st Jan, 1st May and 1st August
2018. Their accounts on 30th November, 2018 showed the following
position:
Particulars |
Contract
I |
Contract
II |
Contract
III |
|
Rs |
Rs |
Rs |
Contract
price |
80,000
|
54,000
|
60,000
|
Materials |
14,400
|
11,600
|
4,000
|
Wages |
22,000
|
22,500
|
2,800
|
General
expenses |
800
|
550
|
200
|
Cash
received for work certified |
30,000
|
24,000
|
5,400
|
Work
certified |
40,000
|
32,000
|
7,200
|
Work
uncertified |
1,200
|
1,600
|
400
|
Wages
outstanding |
700
|
750
|
350
|
General
expenses outstanding |
150
|
100
|
50
|
Plant
installed |
4,000
|
3,200
|
2,400
|
Materials
on hand |
800 |
800 |
400 |
On the respective dates of the contracts, the plant
was installed depreciation thereon being taken at 15% p.a. You are required to
prepare the Contract Accounts.
Solution: 3
Contract
accounts
Particulars |
I |
II |
III |
Particulars |
I |
II |
III |
|
Rs |
Rs |
Rs |
|
Rs |
Rs |
Rs |
To D/Materials |
14,400 |
11,600 |
4,000 |
By D/Mat. on hand |
800 |
800 |
400 |
To D/Wages
(Including o/s) |
22,700 |
23,250 |
3,150 |
By Value of work
Certified |
40,000 |
32,000 |
7,200 |
To Gen. Expenses
(Including o/s) |
950 |
650 |
250 |
By Cost of work
Not certified |
1,200 |
1,600 |
400 |
To Dep. on Plant
[W.N. 1] |
550 |
280 |
120 |
By P/L A/c (Loss
Transferred) |
|
1,380 |
|
To Notional profit |
3,400 |
|
480 |
|
|
|
|
|
42,000 |
35,780 |
8,000 |
|
42,000 |
35,780 |
8,000 |
To P/L A/c [W.N. 3] |
1,700 |
|
|
By Notional profit |
3,400 |
|
480 |
To WIP Provision |
1,700 |
|
480 |
|
|
|
|
|
3,400 |
|
480 |
|
3,400 |
|
480 |
|
|
|
|
|
|
|
|
Working notes:
1.
Depreciation on plant
Contract I |
Rs 4,000 × 15% × 11/12 |
Rs 550 |
Contract II |
Rs 3,200 × 15% × 7/12 |
Rs 280 |
Contract III |
Rs 2,400 × 15% × 4/12 |
Rs 120 |
2.
Percentage completion
Contract I |
(Rs 40,000 ÷ Rs 80,000) × 100% |
50% |
Contract II |
Not required, because incurred loss |
|
Contract III |
(Rs 7,200 ÷ Rs 60,000) × 100% |
12% |
3.
Profit to be transferred to P/L A/c
Contract I |
3,400 × (30,000 ÷ 40,000) × 2/3 |
Rs 1,700 |
Contract II |
Entire loss transferred to P/L A/c |
|
Contract III |
Percentage completion is less than
25% |
Nil |
Illustration:
4
The following is the Trial Balance of Premier
Construction Company, engaged on the execution of contract No.747, for the year
ended 31st December, 2018.
Particulars |
Debit (Rs) |
Credit (Rs) |
Amount received |
|
3,60,000 |
Buildings |
1,60,000 |
|
Creditors |
|
72,000 |
Bank Balance |
95,000 |
|
Capital Account |
|
5,00,000 |
Materials |
2,00,000 |
|
Wages |
1,80,000 |
|
Expenses |
47,000 |
|
Plant |
2,50,000 |
|
|
9,32,000 |
9,32,000 |
The work on Contract No.747 was commenced on 1st
January, 2018. Materials costing Rs 1, 70,000 were sent to the site of
the contract but those of Rs 6,000 were destroyed in an accident. Wages of Rs 1,
80,000 were paid during the year. Plant with a cost of Rs 2 lakhs was used from
1st January to 30th September and was then returned to
the stores. Materials of the cost of Rs 4,000 were at site on 31st December,
2018.
The contract was
for Rs 6, 00,000 and the contractee pays 75% of the work certified. Work
certified was 80% of the total contract at the end of 2018. Uncertified work
was estimated at Rs 15,000 on 31st December, 2018. Expenses are
charged to the contract at 25% of wages. Plant is to be depreciated at 10% for
the entire year.
You are required to prepare:
1. Contract Account;
2. Profit and Loss Account for the year
ended 31st December, 2018; and
3. Balance Sheet as at 31st
December, 2018.
Solution: 4
Contract 747 Account
Particulars |
Rs |
Particulars |
Rs |
To
D/Materials sent to site |
1,70,000 |
By
D/Materials at site |
4,000 |
To
D/Wages |
1,80,000 |
By Abnormal loss of materials |
6,000 |
To
Expenses (1, 80,000 × 25%) |
45,000 |
By Value of work certified [W.N. 2] |
4,80,000 |
To
Dep. on plant [W.N. 1] |
20,000 |
By
Cost of work not certified |
15,000 |
To
Notional Profit c/d |
90,000 |
|
|
|
5,05,000 |
|
5,05,000 |
To
P/L A/c [W.N. 4] |
45,000 |
By
Notional Profit b/d |
90,000 |
To
WIP Provision |
45,000 |
|
|
|
90,000 |
|
90,000 |
P/L A/c for the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To Abnormal loss of materials |
6,000 |
By
Profit from Contract A/c |
45,000 |
To Dep. on plant [W.N. 1] |
5,000 |
|
|
To Expenses (47,000 – 45,000) |
2,000 |
|
|
To
Net Profit (Transferred to B/S) |
32,000 |
|
|
|
45,000 |
|
45,000 |
Balance Sheet as at 31.12.2018
Liabilities |
Rs |
Rs |
Assets |
Rs |
Rs |
Capital: |
|
|
Buildings |
|
1,60,000 |
Opening balance |
5,00,000 |
|
Plant |
2,50,000 |
|
Add: Net Profit |
32,000 |
5,32,000 |
Less: Depreciation |
25,000 |
2,25,000 |
Creditors |
|
72,000 |
Stock of Materials: |
|
|
|
|
|
At Store |
30,000 |
|
|
|
|
At Site |
4,000 |
34,000 |
|
|
|
WIP [W.N. 5] |
4,50,000 |
|
|
|
|
Less: Cash received |
3,60,000 |
90,000 |
|
|
|
Bank A/c |
|
95,000 |
|
|
6,04,000 |
|
|
6,04,000 |
Working
notes:
1.
Depreciation on plant
To be charged to Contract A/c: |
|
|
|
For 1.1.2018 to 30.9.2018 |
2,50,000 × 10% × 9/12 |
Rs
18,750 |
|
For 1.10.2018 to 31.12.2018 |
50,000 × 10% × 3/12 |
Rs
1,250 |
Rs
20,000 |
To be charged to P/L A/c: |
2,00,000 × 10% × 3/12 |
|
Rs
5,000 |
Total depreciation on plant |
|
|
Rs
25,000 |
2.
Value of work certified
⇒ 80% of Contract Price
⇒
80% of Rs 6, 00,000
⇒
Rs 4, 80,000
3. Percentage Completion
= (Value of work certified ÷ Contract Price) × 100%
= (Rs 4, 80,000 ÷ Rs 6, 00,000) × 100%
= 80%
4. Profit to be transferred to P/L A/c
= Notional Profit × (Cash Received ÷ Value of work
certified) × 2/3
= Rs 90,000 × (Rs 3, 60,000 ÷ Rs 4, 80,000) × 2/3
= Rs 45,000
5.
Value
of closing work-in-progress
= Value of work certified + Cost of work
not certified – WIP Provision
= 4, 80,000 + 15,000 – 45,000
= Rs 4, 50,000
Illustration:
5
The following Trial Balance was extracted on 31st
December, 2018 from the books of Swastik Contractors Limited:
Particulars |
Debit (Rs) |
Credit (Rs) |
Share Capital: |
|
|
Shares of Rs 10 each |
|
3,51,800 |
P&L A/c on 1.1. 2018 |
|
25,000 |
Provision for Dep. on Machinery |
|
63,000 |
Cash received on account Contract - 7 |
|
12,80,000 |
Creditors |
|
81,200 |
Land and Buildings (Cost) |
74,000 |
|
Machinery (Cost) |
52,000 |
|
Bank |
45,000 |
|
Contract 7: |
|
|
Materials |
6,00,000 |
|
Direct Labour |
8,30,000 |
|
Expenses |
40,000 |
|
Machinery on site (Cost) |
1,60,000 |
|
|
18,01,000 |
18,01,000 |
Contract 7 was begun on 1st January, 2018.
The contract price is Rs 24, 00,000 and the customer has so far paid Rs 12,
80,000 being 80% of the work certified. The cost of the work done since
certification is estimated at Rs 16,000. On 31st December, 2018,
after the above Trial Balance was extracted machinery costing Rs 32,000 was
returned to stores, and materials then on site were valued at Rs 27,000. Provision
is to be made for outstanding direct labour amounting to Rs 6,000 and for
depreciation of all machinery at 121/2 % on cost.
You are required
to prepare:
(a) The Contract
Account;
(b) The Profit and Loss Account for the year ended 31st
December, 2018; and
(c) The Balance Sheet of Swastik
Contractors Limited as at 31st December, 2018.
Solution: 5
Contract Account
Particulars |
Rs |
Particulars |
Rs |
To
D/Materials sent to site |
6,00,000 |
By
D/Materials at site |
27,000 |
To
D/Labour (Incl. o/s 6,000) |
8,36,000 |
By Value of work certified [W.N. 1] |
16,00,000 |
To
Expenses |
40,000 |
By Cost of work not certified |
16,000 |
To
Dep. on machinery (1, 60,000 × 12.5%) |
20,000 |
|
|
To
Notional Profit c/d |
1,47,000 |
|
|
|
16,43,000 |
|
16,43,000 |
To
P/L A/c [W.N. 3] |
78,400 |
By
Notional Profit b/d |
1,47,000 |
To
WIP Provision |
68,600 |
|
|
|
1,47,000 |
|
1,47,000 |
P/L A/c for the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To
Dep. on machinery (52,000 × 12.5%) |
6,500 |
By
Balance b/d |
25,000 |
To Net Profit (Transferred to B/S) |
96,900 |
By
Profit from Contract A/c |
78,400 |
|
1,03,400 |
|
1,03,400 |
Balance Sheet as at 31.12.2018
Liabilities |
Rs |
Rs |
Assets |
Rs |
Rs |
Share Capital |
|
3,51,800 |
Land and Buildings |
|
74,000 |
P/L A/c balance |
|
96,900 |
Machinery (at cost) |
2,12,000 |
|
Creditors |
|
81,200 |
Less: Depreciation |
89,500 |
1,22,500 |
O/s Direct Labour |
|
6,000 |
Stock of Materials |
|
27,000 |
|
|
|
WIP [W.N. 4] |
15,47,400 |
|
|
|
|
Less: Cash received |
12,80,000 |
2,67,400 |
|
|
|
Bank A/c |
|
45,000 |
|
|
5,35,900 |
|
|
5,35,900 |
Working
notes:
1.
Value of work certified
⇒ Cash received ÷ 80%
⇒
Rs 12, 80,000 ÷ 80%
⇒ Rs 16, 00,000
2. Percentage Completion
= (Value of work certified ÷ Contract Price) × 100%
= (Rs 16, 00,000 ÷ Rs 24, 00,000) × 100%
= 66.67%
3. Profit to be transferred to P/L A/c
= Notional Profit × (Cash Received ÷ Value of work
certified) × 2/3
= Rs 1, 47,000 × (Rs 12, 80,000 ÷ Rs 16, 00,000) × 2/3
= Rs 78,400
4.
Value
of closing work-in-progress
= Value of work certified + Cost of work not
certified – WIP Provision
= 16, 00,000 + 16,000 – 68,600
= Rs 15, 47,400
Construction site
Illustration:
6
The following particulars are obtained from the books
of ViCon Limited as on 31st March, 2018.
Plant and
equipment at cost Rs 4, 90,000
Vehicles at cost
Rs 2, 00,000
Details of
contracts which remain uncompleted as on 31-3-2018 are as follows: (Rs in lacs)
|
Contract
nos. |
||
Particulars |
V.29 |
V.24 |
V.25 |
Estimated
final sales value |
8.00 |
5.60 |
16.00 |
Estimated
total cost |
6.40 |
7.00 |
12.00 |
Actual expenses
incurred: |
|
|
|
Wages |
2.40 |
2.00 |
1.20 |
Materials |
1.00 |
1.10 |
0.44 |
Overheads
(excluding depreciation) |
1.44 |
1.46 |
0.58 |
Total expenses
(excluding dep.) |
4.84 |
4.56 |
2.22 |
Value
certified by architects |
7.20 |
4.20 |
2.40 |
Progress
payments received |
5.00 |
3.20 |
2.00 |
Depreciation of plant and Equipment and Vehicle should
be charged at 20% to the three contracts in proportion to work certified. You
are required to prepare statements showing contract-wise and total –
a)
Profit
/ loss to be taken to the P & L A/c for the year ended 31st March,
2018, and
b)
Work-in-progress
as would appear in the Balance Sheet as at 31-03-2018.
Solution: 6
Contract accounts (Rs in lacs)
Particulars |
V.29 |
V.24 |
V.25 |
Particulars |
V.29 |
V.24 |
V.25 |
|
Rs |
Rs |
Rs |
|
Rs |
Rs |
Rs |
To D/Materials |
1.00 |
1.10 |
0.44 |
|
|
|
|
To D/Wages |
2.40 |
2.00 |
1.20 |
By Value of work
Certified |
7.20 |
4.20 |
2.40 |
To Overheads
(Excl. Dep.) |
1.44 |
1.46 |
0.58 |
|
|
|
|
To Depreciation
[W.N. 1] |
0.72 |
0.42 |
0.24 |
By P/L A/c (Loss
Transferred) |
|
0.78 |
0.06 |
To Notional profit |
1.64 |
|
|
|
|
|
|
|
7.20 |
4.98 |
2.46 |
|
7.20 |
4.98 |
2.46 |
To P/L A/c [W.N. 3] |
1.00 |
|
|
By Notional profit |
1.64 |
|
|
To WIP Provision |
0.64 |
|
|
|
|
|
|
|
1.64 |
|
|
|
1.64 |
|
|
Working notes:
1.
Amount of depreciation charged to
contracts
Depreciation on plant and equipment |
4,90,000 × 20% |
|
Rs
98,000 |
Depreciation on vehicles |
2,00,000 × 20% |
|
Rs
40,000 |
Total depreciation |
|
|
Rs
1,38,000 |
Charged to: |
|
|
|
Contract V.29 |
1,38,000 × (7.20 ÷ 13.80) |
Rs
72,000 |
Rs
0.72 lacs |
Contract V.24 |
1,38,000 × (4.20 ÷ 13.80) |
Rs
42,000 |
Rs
0.42 lacs |
Contract V.25 |
1,38,000 × (2.40 ÷ 13.80) |
Rs
24,000 |
Rs
0.24 lacs |
2.
Profit to be transferred to P/L A/c
(only for Contract V.29)
Estimated total profit = Contract
Price – Estimated Total Cost
=
8.00 – 6.40 = Rs 1.60 lacs
Profit to be transferred to P/L A/c
= Estimated Total Profit × (Cash Received ÷ Contract Price)
= 1.60 × (5.00 ÷ 8.00) = Rs 1.00 lacs
3.
Value of closing work-in-progress (Rs in lacs)
|
V.29 |
V.24 |
V.25 |
Value of work certified |
7.20 |
4.20 |
2.40 |
Add: Cost of work not certified |
- |
- |
- |
Less: WIP Provision |
(0.64) |
- |
- |
Value of closing work-in-progress |
6.56 |
4.20 |
2.40 |
Illustration: 7
Deluxe Limited undertook a contract for Rs 5, 00,000 on 1.7.2018. On
30.6.2019, when the accounts were closed, the following details about the
contract were gathered:
Particulars |
Rs |
Materials
purchased |
1,00,000 |
Wages paid |
45,000 |
General
expenses |
10,000 |
Plant
purchased |
50,000 |
Materials on
hand on 30.6.2011 |
25,000 |
Wages
accrued on 30.6.2011 |
5,000 |
Work
certified |
2,00,000 |
Cash
received |
1,50,000 |
Work
uncertified |
15,000 |
Depreciation
of plant |
5,000 |
The above contract contained an escalation clause which read as
follows:
“In the event of prices of materials and rates of wages increase by more than 5%, the contract price would be increased accordingly by 25% of the rise in the cost of materials and wages beyond 5% in each case.”
It was found that since the date of signing the agreement the prices of materials and rates of wages increased by 25%. The value of the work certified does not take into account the effect of the above clause.
Prepare the contract account. Workings should form part of the answer.
Solution: 7
Contract A/c of Deluxe Limited for the year ended
30.6.2019
Particulars |
Rs |
Particulars |
Rs |
To Materials purchased |
1,00,000 |
By Materials on hand |
25,000 |
To Wages paid Rs 45,000 |
|
By Value of work
certified |
2,00,000 |
ADD:
Accrued Rs 5,000 |
50,000 |
|
|
To General expenses |
10,000 |
By Cost of work
uncertified |
15,000 |
To Plant depreciation |
5,000 |
By Contract price
escalation [W.N. 1] |
5,000 |
To Notional Profit c/d |
80,000 |
|
|
|
2,45,000 |
|
2,45,000 |
To P/L a/c [W.N. 3] |
19,512 |
By Notional Profit b/d |
80,000 |
To WIP provision |
60,488 |
|
|
|
80,000 |
|
80,000 |
Working notes:
1. Contract price escalation
(As per the
Escalation Clause the contract price would be increased because prices of
materials and rates of wages increased by 25%, which is more than the minimum required
5% increase in material prices and wage rates for the contract price to be
increased.)
Particulars |
Rs |
Increase in material price
[(Rs 1,00,000 – Rs 25,000) x (25/125)] |
15,000 |
Increase in wages [(Rs 45,000
+ Rs 5,000) x (25/125)] |
10,000 |
Total increase (when material
price and wages increased by 25%) |
25,000 |
Total increase (when material
price and wages increased by 5%) |
5,000 |
Contract
price escalation [25% of (Rs 25,000 – Rs 5,000)] |
5,000 |
2. Percentage completion
(Value of work certified ÷
Contract price) x 100
= (2, 05,000 ÷ 5, 05,000) x
100 = 40.60%
3. Profit to be transferred to profit
and loss account
Notional profit x (Cash
received ÷ Value of work certified) x 1/3
= 80,000 x (1, 50,000 ÷ 2,
05,000) x 1/3
= Rs 19,512
Illustration: 8
M/s New Century Builders have entered into a contract to build an office building complex for Rs 480 lakh. The work started on 1st April, 2018 and it is estimated that the contract will take 15 months to be completed. Work has progressed as per schedule, and the actual costs charged till 31st March, 2019 are as follows:
Particulars |
Rs
(in lacs) |
Materials |
112.20 |
Labour |
162.00 |
Hire charges for equipments |
36.00 |
Establishment charges |
32.40 |
Total |
342.60 |
The following information is available:
Particulars |
Rs
(in lacs) |
Materials in hand as on 31st March, 2019 |
6.60 |
Work certified as on 31st March, 2019 |
400.00 |
On account payment received till 31st
March, 2019 |
324.00 |
Work not yet certified as on 31st March,
2019 |
7.50 |
As per management estimates, the following further expenditure will be incurred to complete the work:
Particulars |
Rs
(in lacs) |
Materials |
10.50 |
Labour |
16.00 |
Sub-contractors |
20.00 |
Hire charges for equipments |
3.00 |
Establishment charges |
6.90 |
You are required to compute the value of
work-in-progress as on 31st March, 2019 after considering a
reasonable margin of profit and to show the appropriate accounts. Make a
provision for contingencies amounting to 5% of the total costs after charging
such provision.
Solution: 8
Contract account (Rs in lacs)
Particulars |
Rs |
Particulars |
Rs |
To Materials |
112.20 |
By Materials in hand |
6.60 |
To
Labour |
162.00 |
By Cost of work not certified |
7.50 |
To Hire charges for equipments |
36.00 |
By Value of work certified |
400.00 |
To
Establishment charges |
32.40 |
|
|
To
Notional profit c/d |
71.50 |
|
|
|
414.10 |
|
414.10 |
To
P/L a/c [W.N. 2] |
40.50 |
By
Notional profit b/d |
71.50 |
To WIP provision |
31.00 |
|
|
|
71.50 |
|
71.50 |
Working
notes:
1. Estimated total profit: (Rs
in lacs)
Particulars |
Rs |
Rs |
Total cost up-to-date: |
|
|
Materials (112.20 – 6.60) |
105.60 |
|
Labour |
162.00 |
|
Hire charges for equipment |
36.00 |
|
Establishment charges |
32.40 |
336.00 |
Add: Estimated further cost: |
|
|
Materials (6.60 + 10.50) |
17.10 |
|
Labour |
16.00 |
|
Sub-contractors |
20.00 |
|
Hire charges for equipment |
3.00 |
|
Establishment charges |
6.90 |
63.00 |
Estimated total cost excluding provision |
|
399.00 |
Add: Provision for contingencies: (399.00 x 5 ÷ 95) |
|
21.00 |
Estimated total cost including provision |
|
420.00 |
Contract price |
|
480.00 |
Estimated total profit |
|
60.00 |
2. Profit to be transferred to profit
and loss account:
Estimated total profit x (Cash received ÷
Contract price)
= 60.00 x (324.00 ÷ 480.00) = Rs 40.50 Lakh
3. Value of work-in-progress (WIP):
Value of work certified + Cost of work not
certified − WIP Provision
= 400.00 + 7.50 − 31.00 = Rs 376.50 Lakh
Illustration: 9
United Construction Company got a contract in January,
2018 for construction of a bridge. The contract price was Rs 5, 00,000. The
Company incurred the following expenses up to 31st December, 2018:
Particulars |
Rs |
Materials issued |
1,10,000 |
Wages |
40,000 |
Direct expenses |
20,000 |
Plant purchased on 30th June, 2018 |
1,00,000 |
Materials in hand |
5,000 |
Cost of uncertified work |
2,000 |
Depreciation is to be charged on plant @ 10% per
annum. Other works expenses are to be charged
@ 20% of wages and office expenses are to be charged @ 10% of works
cost. The value of work certified by the engineer up to 31st
December, 2018 was Rs 3, 00,000 retention money being 20% of the certified
value.
Prepare a Contract Account showing therein the amount
of profit or loss to be transferred to profit and loss account.
Solution: 9
Contract account
Particulars |
Rs |
Particulars |
Rs |
To Materials |
1,10,000 |
By Materials in hand |
5,000 |
To
Labour |
40,000 |
By Cost of work not certified |
2,000 |
To Direct expenses |
20,000 |
By Value of work certified |
3,00,000 |
To Depreciation on plant (1,00,000
x 10% x 6/12) |
5,000 |
|
|
To
Other works expenses [40,000 x 20%] |
8,000 |
|
|
To Office expenses
[{(1,10,000 – 5,000)
+40,000+20,000+5,000 +8,000} x
10%] |
17,800 |
|
|
To Notional profit c/d |
1,06,200 |
|
|
|
3,07,000 |
|
3,07,000 |
To P/L a/c
[W.N. 2] |
56,640 |
By
Notional profit b/d |
1,06,200 |
To WIP provision (b/f) |
49,560 |
|
|
|
1,06,200 |
|
1,06,200 |
Working notes:
1.
Percentage completion:
(Value of work certified ÷ Contract price)
x 100
= (3, 00,000 ÷ 5, 00,000) x 100 = 60%
2.
Profit to be transferred to profit and
loss account:
Notional profit x (Cash received ÷ Value of
work certified) x 2/3
= 1, 06,200 x (2, 40,000 ÷ 3, 00,000)
x 2/3 = Rs 56,640
Illustration: 10
MK Construction Ltd. entered into a contract to
construct a building. The contract value is Rs 6, 50,000 to be realised in
instalments on the basis of the value of work certified by the architect
subject to retention of 10%. The work commenced on 1.4.2018 but it remained
incomplete on 31.12.2018 when the final accounts are to be prepared. The facts
and figures of the contract are:
Particulars |
Rs |
Plant charged to contract at the commencement |
32,000 |
Materials charged to contract |
1,80,000 |
Wages paid |
87,000 |
Expenses incurred on the contract |
38,750 |
Total establishment expenses amounted to Rs 41,000 out of which 25% is attributable to this contract. Out of the materials issued to the contract, materials costing Rs 4,000 were sold for Rs 5,000. A part of the plant (costing Rs 2,000) was damaged on 1.10.2018 and the scrap realised Rs 300 only. Plant, costing Rs 3,000, was transferred to another contract site on 31.12.2018. Plant is to be depreciated @ 10% p.a.
Other information is:
Particulars |
Rs |
Materials in hand on 31.12.2010 |
17,500 |
Cash received from the contractee |
3,06,000 |
Cost of work yet to be certified |
30,000 |
Prepare a Contract Account showing therein the amount
of profit or loss to be transferred to profit and loss account and compute the
value of work-in-progress as on 31.12.2018.
Solution: 10
Contract
account
Particulars |
Rs |
Particulars |
Rs |
To Materials |
1,80,000 |
By Sale of materials at site |
5,000 |
To
Labour |
87,000 |
By Closing materials at site |
17,500 |
To Direct expenses |
38,750 |
By Profit and loss A/c (abnormal loss due
to plant damaged) Cost of
plant 2,000 (−)
Depreciation 100 [2,000 x
10/100 x 6/12] (−) Scrap
realised 300 |
1,600 |
To Plant sent to site |
32,000 |
By Sale of scrap of plant |
300 |
To Establishment expenses |
10,250 |
By Plant transferred to other site Cost of
plat 3,000 (−)
Depreciation 225 [3,000 x
10/100 x 9/12] |
2,775 |
To
Profit and loss A/c (profit on sale of materials) |
1,000 |
By Plant at site Cost of
plat 27,000
(−)Depreciation 2,025 [27,000 x
10/100 x 9/12] |
24,975 |
|
|
By Cost of work not certified |
30,000 |
To Notional Profit c/d |
73,150 |
By Value of work certified [3,06,000
x 100/90] |
3,40,000 |
|
4,22,150 |
|
4,22,150 |
To P/L a/c
[W.N. 2] |
43,890 |
By
Notional Profit b/d |
73,150 |
To WIP provision |
29,260 |
|
|
|
73,150 |
|
73,150 |
Working notes:
1.
Percentage completion:
(Value of work certified ÷ Contract price)
x 100
= (3, 40,000 ÷ 6, 50,000) x 100 = 52.3%
2.
Profit to be transferred to profit and
loss account:
Notional profit x (Cash received ÷ Value of
work certified) x 2/3
= 73,150 × (3, 06,000 ÷ 3, 40,000) × 2/3
= Rs 43,890
3.
Value of work-in-progress (WIP):
Value of work certified + Cost of work not
certified − WIP Provision
= 3, 40,000
+ 30,000 − 29,260 = Rs 3, 40,740
Construction site
Illustration: 11
Nilcom Construction Company commenced a contract on 1.7.2018.
The contract price is Rs 9, 00,000. Actual expenditure till 31.12.2018 and
estimated expenditure in 2019 are given below:
Particulars |
Actual till 31.12.18 (Rs) |
Estimated for 2019
(Rs) |
Purchase of materials |
1,50,000 |
2,60,000 |
Labour |
1,10,000 |
1,20,000 |
Purchase of plant (original cost) |
80,000 |
− |
Miscellaneous expenses |
40,000 |
71,000 |
|
As at 31.12.18
(Rs) |
As at 30.9.19
(Rs) |
Return of plant to stores (original cost) |
20,000 |
50,000 |
Materials at site |
10,000 |
Nil |
Work certified |
4,00,000 |
Full |
Work uncertified |
15,000 |
Nil |
Cash received |
3,60,000 |
Full |
Depreciation is charged on plant @ 20% p.a. on
original cost (calculation to be made on time basis). The contract is likely to
be completed by 30.9.2019.
You are required to prepare the contract account for
the year ended 31.12.2018. It has been decided to estimate the total profit on
the contract and to take to the credit of profit and loss account that
proportion of estimated profit on realised basis which the work actually
certified bears to the total contract.
Solution: 11
Contract
account of Nilcom Construction Company
For
the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To Materials purchased |
1,50,000 |
By Materials at site |
10,000 |
To Labour |
1,10,000 |
By Plant at site
(depreciated value) |
54,000 |
To Plant purchased |
80,000 |
By Plant returned to store
(depreciated value) |
18,000 |
To Miscellaneous expenses |
40,000 |
By Cost of work uncertified |
15,000 |
To
Notional profit c/d |
1,17,000 |
By Value of work certified |
4,00,000 |
|
4,97,000 |
|
4,97,000 |
To P/L A/c [W.N. 6] |
52,800 |
By
Notional profit b/d |
1,17,000 |
To WIP provision |
64,200 |
|
|
|
1,17,000 |
|
1,17,000 |
Working notes:
Sl.
No. |
Particulars |
Rs |
1 |
Plant
returned to store on 31.12.2018: |
|
|
Original cost |
20,000 |
|
LESS: Depreciation for 6 months @ 20% |
2,000 |
|
|
18,000 |
2 |
Plant
at site on 31.12.2018: |
|
|
Original cost (Rs 80,000 – 20,000) |
60,000 |
|
LESS: Depreciation for 6 months @ 20% |
6,000 |
|
|
54,000 |
3 |
Plant
returned to store on 30.9.2019: |
|
|
Original cost |
50,000 |
|
LESS: Depreciation for 15 months @ 20% |
12,500 |
|
|
37,500 |
4 |
Plant
at site on 30.9.2019: |
|
|
Original cost (Rs 80,000 − 20,000 − 50,000) |
10,000 |
|
LESS: Depreciation for 15 months @ 20% |
2,500 |
|
|
7,500 |
5. Estimated total profit:
Particulars |
Rs |
Rs |
Total cost up-to-date: |
|
|
Materials (1,50,000 – 10,000) |
1,40,000 |
|
Labour |
1,10,000 |
|
Plant (80,000 – 54,000 – 18,000) [Alternative calculation: Rs 80,000 × 20% × 6/12] |
8,000 |
|
Miscellaneous expenses |
40,000 |
2,98,000 |
Add: Estimated further cost: |
|
|
Materials (10,000 + 2,60,000) |
2,70,000 |
|
Labour |
1,20,000 |
|
Plant (54,000 – 7,500 – 37,500) [Alternative calculation: Rs 60,000 × 20% × 9/12] |
9,000 |
|
Miscellaneous expenses |
71,000 |
4,70,000 |
Estimated total cost |
|
7,68,000 |
Contract price |
|
9,00,000 |
Estimated total profit |
|
1,32,000 |
6. Profit to be transferred to profit and loss account:
Estimated total profit x (Cash received ÷
Contract price)
= 1, 32,000 x (3, 60,000 ÷ 9, 00,000) = Rs 52,800
Illustration: 12
On 1.4.2018 Bill Ltd. commenced work on a contract which was to be completed by 30.6.2019 at an agreed price of Rs 5, 20,000. From the following information you are required to prepare the Contract Account for the year ended 31.12.2018 and show the calculation of the sum to be credited to the profit and loss account for that year.
Bill Ltd.’s financial year ended on 31.12.2018, and on
that day expenditure on the contract totalled Rs 2, 63,000 made up as follows:
Particulars |
Rs |
Plant |
30,000 |
Materials |
1,24,000 |
Wages |
95,000 |
Sundry expenses |
5,000 |
Head Office charges |
9,000 |
Total |
2,63,000 |
Cash totalling Rs 1, 95,000 had been received by 31.12.2018 representing 75% of the work certified till that date. Cost of work completed but not certified till that date was Rs 30,000. A sum of Rs 9,000 had been obtained from the sale of some unsuitable materials which had cost of Rs 8,000. On 31.12.2018 stocks of unused materials on site had cost of Rs 10,000 and the plant was valued at Rs 20,000.
To complete the contract by 30.6.2019 it was estimated
that −
(a)
The
following additional expenditure would be incurred:
Particulars |
Rs |
Wages |
64,000 |
Materials |
74,400 |
Sundry expenses |
9,000 |
(b) Further
plant costing Rs 25,000 would be required;
(c) The
residual value of all plant as at 30.6.2019 would be Rs 15,000;
(d) Head office
charges to the contract would be at the same annual rate plus 10%.
It was estimated that the contract would be completed
on time, but that a contingency provision of Rs 15,000 should be made. From
this estimate and the expenditure already incurred, it was decided to estimate
the total profit that would be made on the contract and to take to the credit
of the profit and loss account for the year ended 31.12.2018, that proportion
of the total profit as it relates to the work actually certified to that date.
Solution: 12
Contract
A/c of Bill Limited for the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To Plant |
30,000 |
By Materials at site |
10,000 |
To Materials |
1,24,000 |
By Plant at site (depreciated value) |
20,000 |
To Wages |
95,000 |
By Bank (sale of materials) |
9,000 |
To Sundry expenses |
5,000 |
By Cost of work uncertified |
30,000 |
To Profit and loss account (profit on
sale of materials) |
1,000 |
By Value of work certified [(1,95,000
x (100 ÷ 75)] |
2,60,000 |
To Head office charges |
9,000 |
|
|
To
Notional Profit |
65,000 |
|
|
|
3,29,000 |
|
3,29,000 |
To P/L a/c
[W.N. 2] |
32,250 |
By
Notional Profit |
65,000 |
To WIP provision |
32,750 |
|
|
|
65,000 |
|
65,000 |
Working
notes:
1. Estimated total profit:
Particulars |
Rs |
Rs |
Total costs incurred up to 31.12.2018: |
|
|
Plant (30,000 – 20,000) |
10,000 |
|
Materials (1,24,000 – 8,000 – 10,000) |
1,06,000 |
|
Wages |
95,000 |
|
Sundry expenses |
5,000 |
|
Head office charges |
9,000 |
2,25,000 |
Add: Estimated further cost: |
|
|
Plant (20,000 + 25,000 – 15,000) |
30,000 |
|
Materials (10,000 + 74,400) |
84,400 |
|
Wages |
64,000 |
|
Sundry expenses |
9,000 |
|
Head office charges [{(9,000 ÷ 9) x 6} x 1.10] |
6,600 |
1,94,000 |
|
|
4,19,000 |
Add: Provision for contingencies: |
|
15,000 |
Estimated total cost |
|
4,34,000 |
Contract price |
|
5,20,000 |
Estimated total profit |
|
86,000 |
2. Profit to be transferred to profit and loss account:
Estimated total profit x (Cash received ÷
Contract price)
= 86,000 x (1, 95,000 ÷ 5, 20,000) = Rs 32,250
Illustration: 13
Deluxe Limited undertook a contract for Rs 5, 00,000
on 1st January, 2018. The company furnishes the following details
for the year ended 31st December, 2018:
Particulars |
Rs |
Materials consumed |
1,65,000 |
Direct expenses |
5,000 |
Wages |
30,000 |
Materials returned to stores |
5,000 |
Materials stolen from site |
10,000 |
Insurance claim admitted |
6,000 |
Other works expenses @ 20% on wages. |
|
Office expenses @ 10% on works cost. |
|
Materials in hand on 31st December, 2018 |
15,000 |
Cash received to the extent of 90% of works
certified |
2,70,000 |
Cost of works uncertified |
11,000 |
Plant sent to site cost Rs 60,000 with a scrap value of Rs 10,000 and a useful life of 5 years. The plant was used in the contract for 146 days.
Prepare contract account showing therein the cost of
materials issued to the site and the amount of profit or loss to be transferred
to the profit and loss account. Show also the value of work-in-progress
separately.
Solution: 13
Contract
A/c of Deluxe Ltd. for the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
||
To Materials issued to site [W.N. 1] |
1,95,000 |
By Materials stolen 10,000 |
|
||
|
|
Less: Ins. Claims admitted 6,000 |
4,000 |
||
To
Wages |
30,000 |
By Insurance claim admitted |
6,000 |
||
To Direct expenses |
5,000 |
By Materials returned to store |
5,000 |
||
To Depreciation on plant [W.N. 2] |
4,000 |
By Materials in hand at site |
15,000 |
||
To
Other works expenses [30,000 x 20%] |
6,000 |
By Cost of works uncertified |
11,000 |
||
To Office expenses [W.N. 3] |
21,000 |
By Value of works certified [W.N. 4] |
3,00,000 |
||
To Notional profit c/d |
80,000 |
|
|
||
|
3,41,000 |
|
3,41,000 |
||
To P/L A/c [W.N. 6] |
48,000 |
By
Notional profit b/d |
80,000 |
||
To WIP provision [b/f] |
32,000 |
|
|
||
|
80,000 |
|
80,000 |
||
Working
notes:
1. Materials issued to site:
|
Rs |
Materials consumed |
1,65,000 |
Add: Materials returned |
5,000 |
Add: Materials stolen |
10,000 |
Add: Materials in hand at site |
15,000 |
|
1,95,000 |
2. Depreciation on plant:
Depreciation per annum |
(Rs 60,000 – 10,000) ÷ 5 = Rs 10,000 |
Depreciation for the accounting period |
(Rs 10,000 ÷ 365) × 146 = Rs 4,000 |
3. Office expenses:
|
Rs |
Materials consumed |
1,65,000 |
Add: Direct wages |
30,000 |
Add: Direct expenses |
5,000 |
Add: Depreciation on plant |
4,000 |
Add: Other works expenses |
6,000 |
Works cost |
2,10,000 |
∴ Office expenses [10% of
works cost] |
21,000 |
4. Value of work certified:
Cash received |
Rs 2,70,000 |
∴ Value of work certified |
Rs 2,70,000 × 100/90 = Rs
3,00,000 |
5. Percentage completion:
(Value of work certified ÷ Contract price)
x 100
= (3, 00,000 ÷ 5, 00,000) x 100 = 60%
6. Profit to be transferred to profit and loss account:
Notional profit x (Cash received ÷ Value of
work certified) x 2/3
= 80,000 x
(2, 70,000 ÷ 3, 00,000) x 2/3 = Rs 48,000
Illustration: 14
Modern Construction Company, with a paid up share
capital of Rs 50 lakhs undertook a contract for constructing LIG Houses. The
contract price was Rs 50 lakhs and the work commenced on 1-1-2018. Cash
received on account of contract on 31-12-2018 was Rs 18 lakhs (90% of the work
was certified). Work completed but not certified was estimated at Rs 1, 00,000.
As on 31-12-2018 material at site was estimated at Rs 30,000 and machinery costing
Rs 2, 00,000 was returned to store. Plant and machinery are to be depreciated
at 5% on original cost. Wages outstanding on 31-12-2018 was Rs 5,000.
The following were the ledger balances (Dr.) as per the
Trial Balance as on 31-12-2018:
Ledger Accounts |
Balances (Rs) |
Land and building |
15,00,000 |
Plant and machinery at cost (60% at site) |
25,00,000 |
Lorries and other vehicles |
8,00,000 |
Furniture |
50,000 |
Materials sent to site |
14,00,000 |
Other equipments |
10,000 |
Fuel and power |
1,25,000 |
Site expenses |
5,000 |
Postage and telegram |
4,000 |
Office expenses |
8,000 |
Rent and rates |
15,000 |
Cash at bank |
1,33,000 |
Wages |
2,50,000 |
Prepare:
1. Contract
account for the year ended 31-12-2018,
2. Profit and
loss account for the year ended 31-12-2018, and
3. Balance sheet
as at 31-12-2018.
Solution: 14
Contract
A/c of Modern Construction Company
For
the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To Materials sent to site |
14,00,000 |
By Materials at site |
30,000 |
To
Wages (Including o/s wages) |
2,55,000 |
By Value of work certified [W.N.2] |
20,00,000 |
To Site expenses |
5,000 |
By Cost of work not certified |
1,00,000 |
To Dep. on P/M [WN: 1] |
85,000 |
|
|
To Fuel and power |
1,25,000 |
|
|
To Notional profit c/d |
2,60,000 |
|
|
|
21,30,000 |
|
21,30,000 |
To P/L a/c
[W.N. 4] |
78,000 |
By
Notional profit b/d |
2,60,000 |
To WIP provision (bal. figure) |
1,82,000 |
|
|
|
2,60,000 |
|
2,60,000 |
Profit and loss account for the year ended 31.12.2018
Particulars |
Rs |
Particulars |
Rs |
To Postage and telegram |
4,000 |
By Contract A/c (proportion of Notional Profit) |
78,000 |
To Office expenses |
8,000 |
|
|
To Dep. on P/M [WN: 1] |
40,000 |
|
|
To Rent and rates |
15,000 |
|
|
To Net profit (transferred to
balance sheet) |
11,000 |
|
|
|
78,000 |
|
78,000 |
Balance
sheet as on 31.12.2018
Liabilities |
Rs |
Assets |
Rs |
Share capital |
50,00,000 |
P/M at cost
25,00,000 |
|
Net profit |
11,000 |
Less: Depreciation (1,25,000) |
23,75,000 |
Outstanding wages |
5,000 |
Land and building |
15,00,000 |
|
|
Lorries and other vehicles |
8,00,000 |
|
|
Furniture |
50,000 |
|
|
Other equipments |
10,000 |
|
|
Stock of materials |
30,000 |
|
|
Work-in-progress [W.N. 5] 19,18,000 |
|
|
|
Less: Cash received (18,00,000) |
1,18,000 |
|
|
Cash at bank |
1,33,000 |
|
50,16,000 |
|
50,16,000 |
Working
notes:
1. Depreciation on plant and machinery:
Particulars |
Rs |
Plant and machinery at site on 31-12-2018 (at cost) [60% of 25,00,000] |
15,00,000 |
ADD: Plant and machinery returned to store from site on
31-12-2018 (at cost) |
2,00,000 |
Plant and machinery used in the contract during 2018
(at cost) |
17,00,000 |
Depreciation on plant and machinery charged to
contract [5% of 17,00,000]
(A) |
85,000 |
Depreciation on plant and machinery directly charged
to P/L A/c [5% of (25,00,000 – 17,00,000)]
(B) |
40,000 |
Total depreciation on plant and machinery [A + B] |
1,25,000 |
2. Value of work certified:
Cash received |
Rs 18,00,000 |
∴ Value of work certified |
Rs 18,00,000 × 100/90 = Rs
20,00,000 |
3. Percentage completion:
(Value of work certified ÷ Contract price)
x 100%
= (20, 00,000 ÷ 50, 00,000) x 100% = 40%
4. Profit to be transferred to profit and loss account:
Notional profit x (Cash received ÷ Value of
work certified) x 1/3
= 2, 60,000 x (18, 00,000 ÷ 20, 00,000) x 1/3
= Rs
78,000
5. Work-in-progress:
= Value of work certified + Cost of work not certified
– WIP Provision
= 20, 00,000 + 1, 00,000 – 1, 82,000 = Rs 19, 18,000
Illustration: 15
Reliable Construction Limited commenced a contract on 1st April, 2018. The total contract was for Rs 49, 21,875. It was decided to estimate the total profit on the contract and to take to the credit of profit and loss account that proportion of estimated profit on cash basis which work completed bore to total contract. Actual expenditure for the period 1st April, 2018 to 31st March, 2019 and estimated expenditure for the period 1st April, 2019 to 30th September, 2019 are given below:
Particulars |
1.4.2018 to 31.3.2019 Actuals (Rs) |
1.4.2019 to 30.9.2019 Estimated (Rs) |
Materials issued |
7,76,250 |
12,99,375 |
Labour: |
|
|
Paid |
5,17,500 |
6,18,750 |
Prepaid |
37,500 |
− |
Outstanding |
12,500 |
5,750 |
Plant purchased |
4,00,000 |
− |
Expenses: |
|
|
Paid |
2,25,000 |
3,75,000 |
Outstanding |
25,000 |
10,000 |
Prepaid |
15,000 |
− |
Plant returns to store (historical cost) |
1,00,000 (on 30.9.2018) |
3,00,000 (on 30.9.2019) |
Work certified |
22,50,000 |
Full |
Work uncertified |
25,000 |
− |
Cash received |
18,75,000 |
− |
Materials at site |
82,500 |
42,500 |
The plant is subject to annual depreciation @ 25% on
written down value method. The contract is likely to be completed on 30th
September, 2019.
Required: Prepare the contract account and determine the profit
on the contract for the year ending on 31st March, 2019 on prudent
basis, which has to be credited to profit and loss account.
Solution: 15
Contract
A/c of Reliable Construction Limited for the year ended 31.3.2019
Particulars |
Rs |
Rs |
Particulars |
Rs |
Rs |
To Materials issued |
|
7,76,250 |
By Plant (Returned): |
|
|
To Wages |
5,17,500 |
|
Cost |
1,00,000 |
|
Add:
Outstanding |
12,500 |
|
Less:
Depreciation |
(12,500) |
87,500 |
Less:
Prepaid |
(37,500) |
4,92,500 |
By Materials at site |
|
82,500 |
To Plant purchased |
|
4,00,000 |
By Plant at site: |
|
|
To Expenses |
2,25,000 |
|
Cost |
3,00,000 |
|
Add:
Outstanding |
25,000 |
|
Less:
Depreciation |
(75,000) |
2,25,000 |
Less:
Prepaid |
(15,000) |
2,35,000 |
By Value of work Certified |
|
22,50,000 |
To Notional Profit c/d |
|
7,66,250 |
By Cost of work
Uncertified |
|
25,000 |
|
|
26,70,000 |
|
|
26,70,000 |
To P/L A/c [W.N. 1, 2] |
|
3,89,000 |
By Notional Profit b/d |
|
7,66,250 |
To WIP Provision (b/f) |
|
3,77,250 |
|
|
|
|
|
7,66,250 |
|
|
7,66,250 |
Working
notes:
1. Estimated total profit:
Particulars |
Rs |
Rs |
Total costs incurred up to 31.3.2019: |
|
|
Plant (12,500 + 75,000) |
87,500 |
|
Materials (7,76,250 – 82,500) |
6,93,750 |
|
Wages |
4,92,500 |
|
Expenses |
2,35,000 |
15,08,750 |
Add: Estimated further cost: |
|
|
Plant [(3,00,000 – 75,000) × 25% × 6/12] |
28,125 |
|
Materials (82,500 + 12,99,375 – 42,500) |
13,39,375 |
|
Wages (6,18,750 + 37,500 – 12,500 + 5,750) |
6,49,500 |
|
Expenses (3,75,000 + 15,000 – 25,000 + 10,000) |
3,75,000 |
23,92,000 |
Estimated total cost |
|
39,00,750 |
Contract price |
|
49,21,875 |
Estimated total profit |
|
10,21,125 |
2. Profit to be transferred to profit and loss account:
Estimated total profit x (Cash received ÷
Contract price)
= 10, 21,125 x (18, 75,000 ÷ 49, 21,875) = Rs 3, 89,000
Click here for Illustration: 16 and
I read this airticle and understood this airticle. This airticle is very easy to understand for student. My suggestion to follow this airtle.
ReplyDeleteThank you Subhadip for your comments. I assure you of publishing more such students-friendly quality articles on different topics of various subjects of CMA and other professional courses.
ReplyDeleteI read this article thoroughly and i understood each and everything. It was very informative which hepled me alot in my preparation for my last examinations. I would like to have more such sort of aticles with same quality from this blog. Further i also want my friends to follow this blog for good quality preparations for their future exams. :)
ReplyDeleteNice and helpful
ReplyDeleteI like this article and it helped me a lot.
ReplyDeleteThis article is easy to understand and helpful.
ReplyDelete