Saturday, September 24, 2022

Cost Accounting - Determination of Machine Hour Rate

 

Cost Accounting

Determination of

Machine Hour Rate


Part A: Discussion of basic theories including the definition of Machine Hour Rate and the methods of computing the Machine Hour Rate for absorption of factory overheads.


Part B: Six Illustrations with solutions


Part A


What is Machine Hour Rate?

In the days of mechanisation of production processes, the most relevant factory overhead absorption rate (also called ‘recovery rate’ and ‘application rate’) to be applied is the machine hour rate. This is the rate calculated by dividing the actual or budgeted overhead cost related to a machine or a group of machines by the appropriate number of machine hours worked or estimated. When budgeted hours are used they are taken at average capacity at which a factory normally operates. You cannot take full capacity hours as the factory may not operate at that level and then the absorption rate may be unnecessarily fixed at a lower level. The overhead costs in a highly mechanised factory are mostly related to the number of hours a machine runs. Hence this is supposed to be the best method for absorbing overhead costs into the cost unit. If a machine normally runs for 2,000 hours per annum and overheads to be absorbed are Rs 50,000 per annum, the machine hour rate will be calculated as (50,000/2,000) i.e. Rs 25 per machine hour. If a job takes 50 hours on that machine, then Rs 1,250 (Rs 25 × 50 hrs) will have to be loaded as cost of using the machine for that job.

 

Computation of Machine Hour Rate

A machine hour rate may be calculated using only those overheads which are directly related to the machine e.g. power, fuel, repairs, maintenance, depreciation etc. These expenses for a period are totalled and then divided by the number of hours worked during the same period (on actual or estimate basis) to compute the required machine hour rate. This is called as Ordinary Machine Hour Rate. Whereas, if costs not related to machine are also included (e.g. supervision, rent, lighting, heating etc.) for the rate calculation, such rate is called as Composite Machine Hour Rate. While calculating machine hour rate, the wages paid to machine operators may also be added to the total costs. This is because these operators directly wok on the machines & thus related to machine operation. In such cases the machine hour rate calculated is called Comprehensive Machine Hour Rate. At times a factory may have more than one similar machines simultaneously working. In such case, a Group Machine Hour Rate may be calculated.

 

Overhead rates are usually calculated for each of the production departments. But sometimes a single overhead rate is also calculated for the entire factory which is known as Blanket Overhead Rate.



Part B


Cost Accounting

Determination of Machine Hour Rate (MHR)

(For Recovery of Factory Overheads)

Selected Problems


Illustration: 1

In a machine department of a factory there are five identical machines. From the particulars given below prepare the machine hour rate for one of the machines.

Space of the department

10,000 Sq. Mt.

Space occupied by the machine

2,000 Sq. Mt.

Cost of the machine

Rs 20,000

Scrap value of the machine

Rs 300

Estimated life of the machine

13 years

Rate of depreciation

7½ % p.a.

Normal running of the machine

2,000 hours p.a.

Power consumed by the machine

Rs 3,000 p.a.

 

Estimated repairs and maintenance throughout the working life of the machine is Rs 5,200. Sundry supplies including oil, waste etc. charged direct to the machine amount to Rs 600 p.a.

 

Other expenses of the department p.a. are:

Rent and Rates

Rs 9,000

Lighting

Rs 400

Supervision

Rs 1,250

Other charges

Rs 5,000

 

It is ascertained that the degree of supervision devoted to this machine is 2/5th remaining 3/5th being devoted to other machines. There are 16 workers in the department of whom 4 are attached to this machine and the remaining to the other machines. Lighting is to be apportioned according to the number of workers employed.

 

Click here for Solution: 1 in PDF


Illustration: 2

From the following particulars compute the Machine hour rate for a machine.

a.            Cost of each machine is Rs 24,000.

b.            Scrap value of each machine is Rs 4,000.

c.            Estimated Working life of each machine is 40,000 hours.

d.           Estimated cost of repairs and maintenance of each machine during the whole life of the machine is Rs 2,000.

e.            Standing charges of the shop for 4 weekly periods are Rs 3,000.

f.                Working hours in 4 weekly periods are 100 hours.

g.            Number of machines in the shop (each of which is liable for equal charge) is 30.

h.            Number of units of power used for each machine per hour is 4 @ 10p per unit.

 

Click here for Solution: 2 in PDF


Illustration: 3

The following particulars relate to a processing machine treating a typical material. You are required to calculate the machine hour rate.

The cost of the machine

Rs 10,000

Estimated life of the machine

10 years

Scrap value of the machine

Rs 1,000

Working hours per annum

(i.e. working hours in 50 weeks @ 44 hours per week)

2,200 hours

Maintenance hours per annum

200 hours

Setting up time per annum (in terms of %-age of total productive time)

5%

Consumption of electricity per hour

16 units

Electricity charge per unit

10 paise

Chemicals required per week

Rs 20

Maintenance cost per year

Rs 1,200

 

Two attendants control the operations of the machine together with 6 other machines. Their combined weekly wages are Rs 140. Departmental overhead allocated to this machine is Rs 2,000 per annum.

 

Click here for Solution: 3 in PDF


Illustration: 4

In a factory there are 5 machines. You are required to calculate the Machine Hour Rate of one particular machine from the following data.

Space of the departments

8,000 Sq. ft.

Cost of each machine

Rs 20,000

Space occupied by each machine

1,600 Sq. ft.

Other relevant information p.a.:

 

Power consumed by each machine

Rs 3,000

Rate of depreciation

7 ½ %

Number of working hours

2,000 hrs

Estimated Repairs for each machine

Rs 520

Rent & Rates of the departments

Rs 9,000

Lighting of the departments

Rs 750

Supervision of the departments

Rs 1,500

Other charges of the departments

Rs 4,000

 

2/5th of the supervision is for this machine. There are three mechanics for the departments drawing Rs 50, Rs 60 and Rs 70 p. m. respectively.

 

Click here for Solution: 4 in PDF


Illustration: 5

You are required to calculate the machine hour rate of a machine from the following particulars.

The cost of the machine

Rs 10,000

Estimated life of the machine

10 years

Scrap value of the machine

Rs 1,000

Working hours per annum

(i.e. working hours in 50 weeks @ 40 hours per week)

2,000 hours

Maintenance cost per year

Rs 1,200

Consumption of electricity per hour

16 units

Electricity charge per unit

10 paise

Chemicals required per week

Rs 20

 

Two attendants control the operations of the machine together with 5 other machines. Their combined weekly wages are Rs 120. Departmental and General overhead allocated to this machine are Rs 2,000 per annum.

 

Click here for Solution: 5 in PDF


Illustration: 6

An engineering company having 25 different types of automatic machines furnishes you the following data for 2021-22 in respect of machine B:

1.

Cost of the machine

Rs 50,000

Life of the machine

10 years

Scrap value of the machine

Nil

 

2. Overhead expenses are:

Factory Rent

Rs 50,000

Heating and Lighting

Rs 40,000

Supervision

Rs 1,50,000

Reserve equipment of machine B

Rs 5,000

 

Area of the factory is 80,000 sq. ft.

Area occupied by machine B 3,000 sq. ft.

 

3.  Wages of operator is Rs 24 per day of 8 hours including all fringe benefits. He attends to one machine when it is under set up and two machines while under operation.

 

4.  Estimated production hours 3,600 p.a.

Estimated set up time in hours 400 p.a.

Power Rs 0.5 per hour (while the machine is in operation)

 

Prepare a schedule of comprehensive machine hour rate and find the cost of the following jobs:

 

 

JOB 1102

JOB 1308

Set up time (Hrs.)

80

40

Operation time (Hrs.)

130

160

 

Click here for Solution: 6 in PDF 


6 comments:

  1. Replies
    1. Thank you Ur Senpai (Akash) for your comments. I'm happy to note that you studied the article thoroughly and it was helpful to you. Please keep on studying the other articles too which are published in this blog and, of course, which are relevant for your preparation for CMA exams and please keep on giving your valuable comments every time you study a new article the way you have given your comments here. Thank you again, thank you very much.

      Delete
  2. It is a very nice article for students of CMA intermediate. I liked it!

    ReplyDelete
  3. Thank you Utsav, thank you very much for your valuable comments. I'm happy to note that you liked the article and you also recommended the article for the CMA Intermediate students.

    ReplyDelete
  4. I am doing CMA Intermediate and having tution from Biswajit Si.I have read this article carefully and found very helpful for my preparation for exams (CMA Group 1). It's my advice to other students of CMA to follow this Blog regularly.

    ReplyDelete
    Replies
    1. Thank you Udit, thank you very much for your valuable comments. I'm happy that you found the article helpful for your preparation for your CMA Intermediate Group: 1 exam. I also thank you for your recommendation of this blog to the other CMA Intermediate Students.

      Delete