Cost Accounting
Determination of
Machine Hour Rate
Part A: Discussion of basic theories including the definition of Machine Hour Rate and the methods of computing the Machine Hour Rate for absorption of factory overheads.
Part B: Six Illustrations with solutions
What is Machine Hour Rate?
In the days
of mechanisation of production processes, the most relevant factory overhead
absorption rate (also called ‘recovery rate’ and ‘application rate’) to be
applied is the machine hour rate. This is the rate calculated by dividing the
actual or budgeted overhead cost related to a machine or a group of machines by
the appropriate number of machine hours worked or estimated. When budgeted
hours are used they are taken at average capacity at which a factory normally
operates. You cannot take full capacity hours as the factory may not operate at
that level and then the absorption rate may be unnecessarily fixed at a lower
level. The overhead costs in a highly mechanised factory are mostly related to
the number of hours a machine runs. Hence this is supposed to be the best
method for absorbing overhead costs into the cost unit. If a machine normally
runs for 2,000 hours per annum and overheads to be absorbed are Rs 50,000 per
annum, the machine hour rate will be calculated as (50,000/2,000) i.e. Rs 25 per
machine hour. If a job takes 50 hours on that machine, then Rs 1,250 (Rs 25 ×
50 hrs) will have to be loaded as cost of using the machine for that job.
Computation of Machine Hour Rate
A machine hour
rate may be calculated using only those overheads which are directly related to
the machine e.g. power, fuel, repairs, maintenance, depreciation etc. These
expenses for a period are totalled and then divided by the number of hours
worked during the same period (on actual or estimate basis) to compute the
required machine hour rate. This is called as Ordinary Machine Hour Rate.
Whereas, if costs not related to machine are also included (e.g.
supervision, rent, lighting, heating etc.) for the rate calculation, such rate
is called as Composite
Machine Hour Rate. While calculating machine hour rate,
the wages paid to machine operators may also be added to the total costs. This
is because these operators directly wok on the machines & thus related to
machine operation. In such cases the machine hour rate calculated is called Comprehensive Machine Hour Rate. At times
a factory may have more than one similar machines simultaneously working. In
such case, a Group Machine Hour Rate may
be calculated.
Overhead rates are usually calculated for each of the
production departments. But sometimes a single overhead rate is also calculated
for the entire factory which is known as Blanket Overhead
Rate.
Part B
Cost Accounting
Determination of Machine
Hour Rate (MHR)
(For Recovery of Factory Overheads)
Selected Problems
Illustration:
1
In a machine department of a factory there are five
identical machines. From the particulars given below prepare the machine hour
rate for one of the machines.
Space of the department |
10,000 Sq. Mt. |
Space occupied by the
machine |
2,000 Sq. Mt. |
Cost of the machine |
Rs 20,000 |
Scrap value of the machine |
Rs 300 |
Estimated life of the
machine |
13 years |
Rate of depreciation |
7½ % p.a. |
Normal running of the
machine |
2,000 hours p.a. |
Power consumed by the
machine |
Rs 3,000 p.a. |
Estimated
repairs and maintenance throughout the working life of the machine is Rs 5,200. Sundry supplies including oil, waste etc.
charged direct to the machine amount to Rs 600 p.a.
Other expenses of the department p.a. are:
Rent and Rates |
Rs 9,000 |
Lighting |
Rs 400 |
Supervision |
Rs 1,250 |
Other charges |
Rs 5,000 |
It is ascertained that the degree of supervision
devoted to this machine is 2/5th remaining 3/5th being devoted to other machines. There are 16
workers in the department of whom 4 are attached to this machine and the
remaining to the other machines. Lighting is to be apportioned according to the
number of workers employed.
Illustration:
2
From the following particulars compute the Machine
hour rate for a machine.
a.
Cost
of each machine is Rs 24,000.
b.
Scrap
value of each machine is Rs 4,000.
c.
Estimated
Working life of each machine is 40,000 hours.
d.
Estimated
cost of repairs and maintenance of each machine during the whole life of the
machine is Rs 2,000.
e.
Standing
charges of the shop for 4 weekly periods are Rs 3,000.
f.
Working
hours in 4 weekly periods are 100 hours.
g.
Number
of machines in the shop (each of which is liable for equal charge) is 30.
h.
Number
of units of power used for each machine per hour is 4 @ 10p per unit.
Illustration:
3
The following particulars relate to a processing
machine treating a typical material. You are required to calculate the machine
hour rate.
The cost of the machine |
Rs 10,000 |
Estimated life of the
machine |
10 years |
Scrap value of the machine |
Rs 1,000 |
Working hours per annum (i.e. working hours in 50
weeks @ 44 hours per week) |
2,200 hours |
Maintenance hours per annum |
200 hours |
Setting up time per annum (in
terms of %-age of total productive time) |
5% |
Consumption of electricity
per hour |
16 units |
Electricity charge per unit |
10 paise |
Chemicals required per week |
Rs 20 |
Maintenance cost per year |
Rs 1,200 |
Two attendants
control the operations of the machine together with 6 other machines. Their
combined weekly wages are Rs 140. Departmental overhead allocated to this
machine is Rs 2,000 per annum.
Illustration:
4
In a factory
there are 5 machines. You are required to calculate the Machine Hour Rate of
one particular machine from the following data.
Space of the departments |
8,000 Sq. ft. |
Cost of each machine |
Rs 20,000 |
Space occupied by each
machine |
1,600 Sq. ft. |
Other relevant information p.a.: |
|
Power consumed by each machine |
Rs 3,000 |
Rate of depreciation |
7 ½ % |
Number of working hours |
2,000 hrs |
Estimated Repairs for each
machine |
Rs 520 |
Rent & Rates of the
departments |
Rs 9,000 |
Lighting of the departments |
Rs 750 |
Supervision of the
departments |
Rs 1,500 |
Other charges of the
departments |
Rs 4,000 |
2/5th
of the supervision is for this machine. There are three mechanics for the
departments drawing Rs 50, Rs 60 and Rs 70 p. m. respectively.
Illustration: 5
You
are required to calculate the machine hour rate of a machine from the following
particulars.
The cost of the machine |
Rs 10,000 |
Estimated life of the
machine |
10 years |
Scrap value of the machine |
Rs 1,000 |
Working hours per annum (i.e. working hours in 50
weeks @ 40 hours per week) |
2,000 hours |
Maintenance cost per year |
Rs 1,200 |
Consumption of electricity
per hour |
16 units |
Electricity charge per unit |
10 paise |
Chemicals required per week |
Rs 20 |
Two attendants
control the operations of the machine together with 5 other machines. Their
combined weekly wages are Rs 120. Departmental and General overhead allocated
to this machine are Rs 2,000 per annum.
Illustration:
6
An engineering company having 25 different types of
automatic machines furnishes you the following data for 2021-22 in respect of
machine B:
1.
Cost of the machine |
Rs 50,000 |
Life of the machine |
10 years |
Scrap value of the machine |
Nil |
2. Overhead expenses are:
Factory Rent |
Rs 50,000 |
Heating and Lighting |
Rs 40,000 |
Supervision |
Rs 1,50,000 |
Reserve equipment of machine
B |
Rs 5,000 |
Area of the factory is 80,000 sq. ft.
Area occupied by machine B 3,000 sq. ft.
3. Wages of
operator is Rs 24 per day of 8 hours including all fringe benefits. He attends
to one machine when it is under set up and two machines while under operation.
4. Estimated production hours 3,600 p.a.
Estimated
set up time in hours 400 p.a.
Power
Rs 0.5 per hour (while the machine is in operation)
Prepare a
schedule of comprehensive machine hour rate and find the cost of the following
jobs:
|
JOB
1102 |
JOB
1308 |
Set up time (Hrs.) |
80 |
40 |
Operation time (Hrs.) |
130 |
160 |
gone through it. Was helpful.
ReplyDeleteThank you Ur Senpai (Akash) for your comments. I'm happy to note that you studied the article thoroughly and it was helpful to you. Please keep on studying the other articles too which are published in this blog and, of course, which are relevant for your preparation for CMA exams and please keep on giving your valuable comments every time you study a new article the way you have given your comments here. Thank you again, thank you very much.
DeleteIt is a very nice article for students of CMA intermediate. I liked it!
ReplyDeleteThank you Utsav, thank you very much for your valuable comments. I'm happy to note that you liked the article and you also recommended the article for the CMA Intermediate students.
ReplyDeleteI am doing CMA Intermediate and having tution from Biswajit Si.I have read this article carefully and found very helpful for my preparation for exams (CMA Group 1). It's my advice to other students of CMA to follow this Blog regularly.
ReplyDeleteThank you Udit, thank you very much for your valuable comments. I'm happy that you found the article helpful for your preparation for your CMA Intermediate Group: 1 exam. I also thank you for your recommendation of this blog to the other CMA Intermediate Students.
Delete