Strategic
Cost Management
Throughput
Costing
Part A
Introduction
Throughput Costing is a management accounting technique used as a performance measure in the
theory of constraints. It is the business intelligence used for maximizing
profits. It focuses importance on generating more throughputs. It seeks to
increase the velocity or speed of production of products and services keeping
in view of constraints. It is based on the concept that a
company must determine its overriding goal
and then it should create a system that clearly defines the main capacity
constraint that allows it to
maximize that goal.
Throughput Costing is a system of performance
measurement and costing which traces costs to throughput time. It is claimed
that it complements JIT principles and forces attention to the true determinants
of profitability. Throughput Costing is defined as follows:
“Throughput Costing is a management
accounting system which focuses on ways by which the maximum return per unit of bottleneck activity can
be achieved” – CIMA Terminology.
Throughput Concepts and
Definitions
Throughput:
Throughput is calculated as
‘selling price less direct material cost.’ This is different
from the calculation of ‘contribution’, in which both labour costs and variable
overheads are also deducted from selling price. In other words, throughput
is the excess of sales value over the totally variable cost. That is nothing but
contribution margin left after a product’s price is reduced by the amount of
its totally variable cost. [Throughput =
Sale Value – Totally Variable Cost (here, Totally Variable Cost = Direct
Material Cost)]
Totally Variable
Cost:
This cost is incurred only if a product is produced.
In many cases only direct materials are considered as totally
variable cost. Direct labour is not totally variable, unless piece
rate wages are paid.
Capacity Constraints:
It is a resource within a
company that limits its total output. For example, it
can be a machine that can produce only a specified amount of a key component in
a given time period, thereby keeping overall sales from expanding beyond the
maximum capacity of that machine. There may be more than one capacity constraint
in a company, but rarely more than one for a specified product or product line.
Total Cycle Time
(TCT):
Total cycle time is the
average time required to convert raw materials into finished goods ready to be
shipped to customer. It includes the time required for activities such as
material handling, production processing, inspecting and packaging.
Total Factory Cost
(TFC):
With the exception of
material costs, in the short run, most factory costs (including direct labour)
are fixed. These fixed costs can be grouped together and called total factory
costs (TFC).
Throughput Efficiency
and Throughput Cost:
Throughput efficiency is the relation of throughput
achieved to resources used.
Throughput efficiency = |
[(Throughput cost) ÷ (Actual
TFC)] × 100% |
Throughput cost = |
Total standard hours on
bottleneck resource for actual production during the period × Cost per
factory hour |
Throughput Time
Ratio:
It is the ratio of time
spent adding customer value to products and services divided by total cycle
time. It is also known as the ‘ratio of work content to lead time’.
Operating Expenses:
This is sum total of all
company expenses including totally variable expenses. It should be noted
that throughput costing does not care, if a cost is semi-variable, fixed or
allocated – all costs that are not totally variable is lumped together for throughput
costing purpose. This group of expenses is considered the price that a company
pays to ensure that it maintains its current level of capacity.
Investment:
This term is used here also, as it is used in common
parlance, i.e. any application of funds, which is intended to provide a return
by way of interest, dividend or capital appreciation. But here, however, there
is a particular emphasis on company’s investment in working capital.
Manufacturing
Response Time:
With JIT, products should not be made unless there is
a customer waiting for them, because the ideal inventory level is zero. The
effect of this will be that there will be idle capacity in some operations
except the operation which is bottleneck at the moment. Working on output just
to increase WIP or Finished Goods stocks creates no profit and so would not be
encouraged.
This means that profit is inversely proportional to
the level of inventory in the system. It can be expressed as follows:
Profit
∝ (1 ÷
MRT)
Where, MRT = Manufacturing
Response Time
Profitability:
This concept emphasises that profitability is determined
by how quickly goods can be produced to satisfy customer’s order. Production for
stock does not create profits. Improving the throughput of bottleneck operations
will increase the rate at which customer demand can be met and will improve the
profitability. Contribution in its traditional form (sales – variable costs) is
not a good guide of profitability because it ignores capacity factors and rate
of production.
(1) |
Return per factory hour (Product-wise) = |
|
(Sales Price per unit – material Cost per unit) ÷ (Product Time per
unit on key resource in hours) |
|
= Throughput per unit ÷ Product Time per unit on key resource in hours |
|
|
(2) |
Cost per factory hour = |
|
Total factory costs (TFC) ÷ Total time available on key resource |
|
|
The return and cost per factory hour are combined into
the Throughput Costing Ratio (TC Ratio) as
follows:
TC Ratio = |
[Return per factory hour (or minute)]
÷ [Cost per factory hour (or minute)] |
The TC Ratio should be
greater than 1. If it is less than 1 the product will lose money for the
company and the company should consider withdrawing it from the market.
The TC ratio can be considered in total terms by
comparing the total return from the throughput with the TFC, i.e.
Primary TC Ratio = |
[Total return from throughput (i.e. Sales-Material Costs)] ÷ [TFC (i.e., all costs other than materials)] |
Throughput Costing and
Contribution Approach
Throughput Costing has certain similarities with the
traditional approach of maximizing contribution per unit of scarce resource.
However, there are certain differences. In throughput costing return is defined
as sales less material costs in contrast to contribution which is sales less
all variable costs, i.e., material, labour, overheads. The assumption (i.e., emphasis)
in throughput costing is that all costs except material are fixed in relation
to throughput in short run. Eminent management accountants like Kaplan and
Shank have criticized throughput costing for its short-term emphasis. Besides,
throughput costing does not appear to be useful in JIT environment. Throughput
helps to direct attention to bottlenecks and forces management to concentrate
on the key elements in making profits and approach adopted to gain this
objective is reduction in inventory and reducing response time to customer
demand.
Basic logic of
throughput costing and
Comparison with
absorption costing
Throughput costing assigns only unit level spending for
direct costs as the cost of products or services. Advocates of throughput costing
argue that adding any other indirect cost, past or committed cost, to product
cost creates improper incentives to drive down the average cost per unit by
making more products than that can be used or sold. Since these are committed
costs, making more units with the same level of spending arithmetically reduces
the average cost per unit and makes the production process appear to be more
efficient. Throughput costing avoids this incentive because the cost per unit
depends only on the unit level spending (i.e., cost of materials) not how many
units are made. Using throughput costing means that cost management analyst
must distinguish between
(a)
Spending for resources caused by the
decision to produce different levels of products and services, and
(b)
The use of resources that organisation
has committed to supply regardless of level of products and services provided.
Steps to be followed
To increase the
throughput
The theory of constraints is applied within an organisation
by following what are called ‘the five focusing steps.’ These are a tool that
Goldratt developed to help organisations deal with constraints, otherwise known
as bottlenecks, within the system as a whole (rather than any discrete unit
within the organisation.) The steps are as follows:
a)
Identify the bottle neck in the system
i.e., identification of the limiting factor of the production (or) process such as installing capacity or hours etc.
b)
Decide how to exploit the systems
bottleneck that means bottleneck resource should be actively and effectively
used as much as possible to produce as many goods as possible.
c)
Subordinate everything else to the
decision made in step (b). The production capacity of the bottleneck resource
should determined production schedule.
d)
Augment the capacity of the bottleneck
resource with the minimum capital input.
e)
Identify the new bottlenecks in the
process and repeat the same above steps to address the bottlenecks.
Problems with throughput
costing
1.
When throughput costing is the driving
force behind all production scheduling, a customer that has already placed an
order for a product, which will result in a sub-optimal profit level for the manufacturing,
may find that its order is never filled.
2.
The company’s ability to create the
highest level of profitability is now dependent on the production scheduling staff, who decides, what products are
to be manufactured and in what order.
3.
Another issue is that all costs are
totally variable in the long-run since the management then, has the time to
adjust them to long-range production volumes.
Reporting under
throughput costing
When the throughput model is used for financial
reporting purposes, the format appears slightly different. The income statement
includes only direct materials in the cost of goods sold, which results in a
‘throughput contribution instead of gross margin. All other costs are jumped
into an ‘Operating Expenses’ category below the throughput contribution margin,
yielding a net income figure at the bottom. All other financial reports stay
the same.
Though this single change appears relatively minor, it
has significant impact. The primary change is that
throughput costing does not charge any operating expenses to
inventory so that they can be expressed in future period. Instead, all
operating expenses are realized
during the current period. As a result, any incentive for managers
to overproduce is completely eliminated because they cannot use the excess
amount to shift expenses out of current period, thereby making their financial
results look better than they would otherwise. Though this is a desirable
result, such a report can be used only for internal reporting because of the requirement
of generally accepted accounting principles that some overheads should be
charged to excess production.
Systematic changes
required
For acceptance of the
throughput costing
Throughput costing does not have a logical linkage
with the more traditional form of cost accounting. This makes it difficult for
it to gain acceptance. The main problem is that this method does not use cost as
the basis for the most optimal production decisions. This is entirely contrary
to the teachings of any other type of costing which holds that the highest
margin products should always be produced first. Now question is whether the
enterprise should either use throughput or traditional costing exclusively or
is there any way to merge the two. Following discussion relates to this issue:
a) Inventory Valuation:
Generally accepted accounting principles clearly state
that cost of overhead must be apportioned to inventory. Throughput costing states
that none of the overhead cost should be so assigned. In this case, since the
rules are so clear, it is apparent that throughput costing loses. The existing system
must continue to assign costs irrespective of how throughput principles are
used for other decision making (short range) activities.
b) Inventory Investment Analysis:
There are fundamental differences between the two
methodologies. Both hold that the objectives always to keep one’s investment at
a minimum. In the case of traditional cost accounting, this is because the return
on investment is higher when the total amount of investment is forced to the lowest
possible level.
Throughput costing, however, wants to shrink the
amount of investment because it includes work-in-progress inventory in this
category. It tries to keep WIP levels down so that waste is reduced in the
production system. In short, first system advocates a small investment for
financial reasons, while later system favours it because it makes more operational
sense. Despite the differences in reasoning, the same conclusion is reached by
both methodologies. However, throughput approach is still better, for it forces
one to analyse all inventory reduction projects in light of how they together
will impact the capacity constraint rather than individually.
c) Capital Investment Analysis:
Traditional cost accounting only analyses each
investment proposal on its own rather than considering its impact on the
production processes as a whole. It tends to recommend investments that will
result in an incremental investment but no overall change in the level of
corporate capacity, which is driven by capacity constraint. Throughput costing,
however, has a tight focus on investment only in areas that impact capacity
constraint – to other investment proposals are rejected. In this instance, it
is best to reject the traditional system and conduct analysis based on throughput
principles.
d) Product Costing:
Under throughput costing, a product has only a totally
variable cost, which may be far lower than the fully absorbed cost that would
be assigned to it under more traditional costing system. This totally variable
cost is almost always direct materials, which is an easily calculated figure.
Full absorption costing, however, requires a large amount of calculation
effort, before a detailed cost can be compiled for a product. For companies
selling to Government under cost-plus contracts, there are lengthy detailed
requirement as to what variable and overhead costs should be assigned to each
product manufactured. These rules virtually require the use of absorption costing
– throughput costing is not a viable solution. For companies, that do not require
detailed costing justifications while selling their products, it may be
possible to use the much simpler throughput costing approach.
e) Production Scheduling:
Traditional systems do not include any kind of throughput
costing that tells production planners which orders should be produced first.
These days with throughput costing, it is possible to customize existing
systems or to upgrade packaged software so that this option is available to planner. This would allow
them to produce the items that result in the highest throughput per minute of
the capacity constraint. Here it is difficult to fully support the throughput
approach. Any company that has already received a customer has an obligation to
fill it, even if the resulting sale will reduce its overall level of profit
from the theoretical maximum that can be calculated with throughput costing.
Maximising short-term profit by ignoring orders is
tantamount to long-term suicide since customers will leave in droves. Consequently,
production planners should be left alone to schedule production in the traditional
manner rather than basing their decisions on short-term profit maximisation.
f) Long-term planning:
This is the main application area of throughput
costing. The enterprise should estimate the approximate sales levels for each
product for a long-time frame enter into a throughput model and determine what
mix of prospective sales will result in the highest level of profitability.
This method is much superior to use of throughput costing for short-term
production decisions, since long-term planning sidesteps problems by avoiding
existing customer orders that will result in low profits. Long-term planning
does not involve existing customer orders so that decisions to produce various
types of products at different price points can be made before the sales force goes
out to obtain order.
g) Price Setting:
Throughput costing is favoured by the sales and
marketing staff favours throughput costing because the margin on products is
simple to obtain-just subtract totally variable costs from the price. This beats
the incomprehensible image of allocations accompanying activity based costing. Price
setting in throughput environment focuses more on what products can be inserted
into the existing production mix at a price that will incrementally increase
overall profitability, rather than the painful accumulation and allocation of
costs to specific products. Throughput costing is the clear choice here based
on case of understandability and the speed with which information can be
accumulated.
Throughput Ratios
There
are three main ratios that are calculated in throughput costing:
1.
Return
per factory hour,
2.
Cost
per factory hour and
3.
Throughput
costing ratio (TC Ratio).
(1) |
Return per factory hour = |
|
Throughput per unit ÷ Product time per unit on bottleneck
resource |
|
|
(2) |
Cost per factory hour = |
|
Total factory costs ÷ Total time available on bottleneck
resource |
|
|
(3) |
Throughput costing ratio (TC Ratio) = |
|
Return per factory hour ÷ Cost per factory hour |
|
|
Strategic
Cost Management
Throughput
Costing Formulas
Total Factory Cost
(TFC):
With the exception of
material costs, in the short run, most factory costs (including direct labour)
are fixed. These fixed costs can be grouped together and called total factory
costs (TFC).
Total Cycle Time
(TCT):
Total cycle time is the
average time required to convert raw materials into finished goods ready to be
shipped to customer. It includes the time required for activities such as
material handling, production processing, inspecting and packaging.
List of
Throughput Costing Formulas
1 |
Throughput = |
|
Sale Value – Totally
Variable Cost [Here, Totally Variable
Cost = Direct Material Cost] |
|
|
2 |
Throughput cost = |
|
Total standard hours on
bottleneck resource for actual production during the period × Cost per
factory hour |
|
|
3 |
Throughput efficiency = |
|
[(Throughput cost) ÷
(Actual TFC)] × 100% |
|
|
4 |
Return (i.e. Throughput) per factory hour (Product-wise) = |
|
[Selling Price per unit – material Cost per unit] ÷ [Product Time per
unit on key (i.e. bottleneck) resource in hours] |
|
= Throughput per unit ÷ Product Time
per unit on key (i.e. bottleneck) resource in hours |
|
|
5 |
Cost per factory hour = |
|
Total factory costs (TFC) ÷ Total time available in hours on key (i.e.
bottleneck) resource |
|
|
6 |
Throughput Costing Ratio
(TC Ratio) = |
|
[Return per factory hour (or minute)] ÷ [Cost per factory hour (or
minute)] |
|
|
7 |
Primary TC Ratio = |
|
[Total return from throughput (i.e. Sales-Material Costs)] ÷ [TFC (i.e., all costs other than materials)] |
|
|
8 |
Throughput Time
Ratio = |
|
It is the ratio of time
spent adding customer value to products and services divided by total cycle
time. It is also known as the ‘ratio of work content to lead time’. |
|
|
Important note:
The TC Ratio should be
greater than 1. If it is less than 1 the product will lose money for the
company and the company should consider withdrawing it from the market.
Part B
Illustration: 1
Modern Co produces 3 products, A, B and C, details of
which are shown below:
Particulars |
A |
B |
C |
Selling price per unit (Rs) |
120 |
110 |
130 |
Direct material cost per unit (Rs) |
60 |
70 |
85 |
Variable overheads (Rs) |
30 |
20 |
15 |
Maximum demand (units) |
30,000 |
25,000 |
40,000 |
Time required on the bottleneck resource per unit (hours) |
5 |
4 |
3 |
There are 3, 20,000
bottleneck hours available each month.
Required:
Calculate the optimum product mix based on the
throughput concept.
Solution: 1
Illustration: 2
A factory has a key resource (bottleneck) of
Facility A which is available for 31,300 minutes per week. Budgeted factory
costs and data on two products, X and Y, are shown below:
Product |
Selling price p.u. |
Material cost p.u. |
Time in Facility A |
X |
Rs 35 |
Rs 20.00 |
5 minutes |
Y |
Rs 35 |
Rs 17.50 |
10 minutes |
Budgeted factory costs per week:
|
Rs |
Direct labour |
25,000 |
Indirect labour |
12,500 |
Power |
1,750 |
Depreciation |
22,500 |
Space costs |
8,000 |
Engineering |
3,500 |
Administration |
5,000 |
Actual production during the last week is 4,750
units of product X and 650 units of product Y. Actual factory cost was Rs 78,250.
Calculate:
1)
Total
factory costs (TFC)
2)
Cost
per Factory Minute
3)
Return
per Factory Minute for both products
4)
Throughput
Costing Ratios for both the products
5)
Throughput
cost per week
6)
Throughput
Efficiency
Solution: 2
Illustration: 3
H Ltd. manufactures three products. The material
cost, selling price and bottleneck resource details per unit are as follows:
Particulars |
Product: X |
Product: Y |
Product: Z |
Selling price (Rs) |
66 |
75 |
90 |
Material cost (Rs) |
24 |
30 |
40 |
Bottleneck resource time |
15 minutes |
15 minutes |
20 minutes |
Budgeted factory costs for the period are Rs 2,
21,600. The bottleneck resources time available is 75,120 minutes per period.
Required:
1.
Company
adopted throughput accounting and products are ranked according to ‘product
return per minute’. Select
the highest rank product.
2.
Calculate
throughput costing ratio and comment on it.
Solution: 3
I read this article thoroughly and i understood each and everything. The presentation made by the blogger is incomparable. I would like to have more such sort of articles with same quality from this blog.
ReplyDeleteThank you Utsav for reading the article thoroughly and giving your valuable comments. I am particularly happy because you understood the topic and could make your concept clear about the same by reading the article. Moreover, I am also pleased to know that you liked the way the article has been arranged and presented. I assure of my all out endeavour to write and publish more such articles of same, may be even better, quality on continuous basis in the days to come.
Delete