PROJECT MANAGEMENT
Network Analysis
Critical Path Method
Definition of Critical Path
Critical
path is the longest path of activities to be performed from start to finish of
a project which can be located and depicted in the Network Diagram drawn before
the construction of the project is started.
All the
activities on the critical path are called “CRITICAL ACTIVITIES”, whereas other
activities of the project are called “NON-CRITICAL ACTIVITIES”.
Determination of Critical Path
Step: 1 – Draw the Network with ES and LF
Draw the network diagram as above.
Fill up the nodes as stated. Earliest Starts
(ES) will be found by Forward Pass Calculations and Latest Finishes
(LF) will be found by Backward Pass Calculations. Forward Pass
Calculations will start at the first event of the network and will finish at
the last event of the network. Backward Pass Calculations will start at the
last event of the network and will finish at the first event of the network.
During
Forward Pass, start at the first event with ‘0’ earliest start and keep on
adding the activity durations for the earliest starts of the rest of the
events. During Backward Pass, start at the last event with the earliest start
of the event as the latest finish of the event and keep on subtracting the
activity durations for the latest finishes of the rest of the events.
During
forward pass, take the highest earliest start time for a ‘merge event’ and
during backward pass, take the lowest latest finish time for a ‘burst event’.
Step: 2 – Find the Critical Path
Following
rules apply in locating the critical path of a network:
Rule 1: Necessary Condition
If, for
an activity, the ES time equals the LF time at both the head of the arrow and
the tail of the arrow, the activity is possibly a critical activity, lying on
the critical path.
Rule 2: Sufficient Condition
If the
first condition is met and the difference between the ES time at the head of
the arrow and the ES time at the tail of the arrow is equal to the duration of
the activity, then the activity is critical and lies on the critical path.
In the above network diagram the critical
path is:
1 – 3 – 6 – 8 (Node number wise)
Normal project duration:
7 + 10 + 5 = 22 days (assuming that
activity durations are in days)
YouTube Link for the Video on above discussion
including solution of the following illustration:
Project Management - Critical Path Method
Illustration:
Information on the activities required for a project
is as follows:
Name of Activities |
Activities by Node(ij) |
Duration (days) |
A |
1 – 2 |
2 |
B |
1 – 3 |
7 |
C |
1 – 4 |
8 |
D |
2 – 5 |
3 |
E |
3 – 5 |
6 |
F |
3 – 6 |
10 |
G |
3 – 7 |
4 |
H |
4 – 6 |
6 |
I |
5 – 7 |
2 |
J |
6 – 8 |
5 |
K |
7 – 8 |
6 |
Draw the network diagram and determine the critical
path and normal project duration.
No comments:
Post a Comment