Project Management
Critical Path Method
Crashing of Project
i) Drawing the Network Diagram,
ii) Identifying the Critical Path,
iii) Determining Normal Project Duration and Normal Project Cost,
iv) Crashing the times of activities and the project duration to arrive at the Optimum Project Completion Time, and
v) Determining the Optimum Project Cost.
Part A
What is project crashing?
A
significant aspect of the CPM network analysis lies in its capacity to evaluate
alternative ways to expedite some (or, if possible, all) of the activities
indicated in a network and then analyse their cost implication. It means, under
CPM technique the duration of some or all of the activities of a project can be
cut down, if some additional resources like men, material and/or equipment are
employed on them.
In general,
the more the time, by which an activity time is required to be cut / crashed,
the greater the amount of resources, that will be required to be employed on
it. Thus, higher amounts of direct activity cost would be associated with
smaller activity duration times, while longer duration times would involve
comparatively lower direct activity costs. In short, for normal duration, direct activity costs involved
will be normal, whereas for smaller duration, direct activity costs involved
will be higher.
In simple terms crashing of project means reducing the activity
times of the project deliberately by putting in extra effort and cost and
thereby reducing the completion time of the entire project from normal level to
an optimum level. In other words, deliberate reduction of activity times
leading to reduction in normal project duration by putting in extra effort and
direct activity costs is called crashing of project.
Project Crashing Procedure
Step: 1 – Computation of ‘Cost-slope’ of
the activities
Cost-slope = |
(Crash cost – Normal cost) ÷ (Normal time – Crash time) |
Step: 2 – Crashing activity
If
there is only one initial critical path, find the critical activity having the
lowest cost-slope. Crash this activity by one day. Draw a new Network Diagram.
Step: 3 – Repeating Step: 2
Repeat
Step: 2 so long there is only one critical path.
Step: 4 – Further crashing of activities
which are common to the critical paths
If
there is more than one critical paths crash those activities which are common
to all the critical paths by as many days as possible. Draw a new Network
Diagram.
Step: 5 – Further crashing of activities
which are not common to the critical paths
At this
stage, same number of days (as maximum as possible) should be crashed
simultaneously from each of the critical paths. Of course, here care should be
taken to ensure that the lowest ‘cost-slope’ activities are crashed first and
then the next lowest ‘cost-slope’ activities in the same order. Draw a new Network
Diagram.
Step: 6 – Repeating Step: 5
Repeat
Step: 5 so long same number of days (as maximum as possible) can be crashed
simultaneously from each of the critical paths ensuring that the lowest
‘cost-slope’ activities are crashed first and then the next lowest ‘cost-slope’
activities in the same order. Draw a new Network Diagram.
Step: 7 – Finding the optimum project
completion time and optimum project cost
When no
further crashing of activities is possible as per the above steps from 2 to 6,
and, therefore, total project duration cannot be reduced any more, optimum
project completion time is reached. Therefore, optimum project completion time
will be the project completion time as per the latest network diagram.
Optimum project cost (Rs) = |
Direct cost + Incremental cost + Indirect
cost |
Direct Cost |
Total of Normal Costs of all the
activities |
Indirect Cost |
Indirect Costs per day × Optimum project completion time |
Table for computation of incremental
cost
Activity |
No of days crashed (DC) |
Cost-slope (CS) |
(DC × CS) |
1 – 2 |
|
|
|
1 – 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Incremental cost (Rs) |
|
Σ(DC × CS) |
Part B
YouTube link for the video on the above discussions including solution of the following illustration.
Please click on the following YouTube Link:
Project Management - Crashing of Project
Critical Path Method
Crashing of Project
Illustration:
The
following table gives data on normal time and cost and crash time and cost for
a project:
Activity |
Normal |
Crash |
||
Time (day) |
Cost (Rs) |
Time (day) |
Cost (Rs) |
|
1 – 2 |
6 |
600 |
4 |
1,000 |
1 – 3 |
4 |
600 |
2 |
2,000 |
2 – 4 |
5 |
500 |
3 |
1,500 |
2 – 5 |
3 |
450 |
1 |
650 |
3 – 4 |
6 |
900 |
4 |
2,000 |
4 – 6 |
8 |
800 |
4 |
3,000 |
5 – 6 |
4 |
400 |
2 |
1,000 |
6 – 7 |
3 |
450 |
2 |
800 |
The
indirect cost per day is Rs 100.
You are required to –
1.
Draw the network and identify the critical path,
2. Determine the normal project duration and normal project cost, and
3.
Crash the relevant activities systematically and determine
i)
The optimum project completion time, and
ii)
The optimum project cost.
No comments:
Post a Comment