Sunday, July 24, 2022

Project Management - Programme Evaluation and Review Technique (PERT)

 

Project Management

Programme Evaluation and Review Technique (PERT)

 

Part A: Discussion about –

1. Method of computation of expected project completion time, and

2. Method of determining the probability of completing a project in a certain fixed completion time.


Part B: YouTube link for the video on the above discussions including solution of one illustration involving -

1. Drawing the Network Diagram of a project,

2. Computation of expected completion time of the project, and

3. Determining the probability of completing the project in a certain fixed number of days.



Part A


Steps for computing the expected project completion time

Step: 1     Drawing the network diagram with optimistic time, most likely time and pessimistic time of each activity,

 

Step: 2     Calculation of expected completion time [T (ij)] and variance of completion time [V (ij)] of each activity,

 

Step: 3     Determining the Critical Path with the expected completion times of the activities,

 

Step: 4     Determining the expected completion time of the project Σ [T (ij)] and variance of completion time of the project Σ [V (ij)] with the expected completion times and variances of completion times respectively of the critical activities on the Critical Path, and

 

Step: 5     Determining the probability of completing the project in a certain fixed completion time.

 


Discussion of the steps 2 to 5 in details


Step: 2

Calculation of expected completion time and variance of completion time of each activity

 

Formulas:

Expected completion time of (i – j) activity,

T(ij) =

[(a + 4m + b) ÷ 6]

Variance of completion time of (i – j) activity,

V(ij) =

[(b a) ÷ 6]^2

Where,

a =

Optimistic Time of completing the (i – j) activity

m =

Most Likely Time of completing the (i – j) activity

b =

Pessimistic Time of completing the (i – j) activity

 

Table for:

Calculation of Expected Completion Times [T (ij)] and Variances of Completion Times [V (ij)] of the Activities

 

Activity

Duration

T(ij) =

V(ij) =

a

m

b

(a + 4m + b) ÷ 6

[(b − a) ÷ 6]^2

1 – 2

 

 

 

 

 

2 – 3

 

 

 

 

 

2 – 4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Step: 3

Critical Path of the project is the longest path from the initial node to the terminal node of the project with the expected completion times of the activities.

 

Step: 4

Computation of –

1

Expected project duration,

μ =

Σ [T (ij)] for the critical path

2

Variance of the

project duration, σ^2 =

[Σ [V (ij)]] for the critical path

3

Standard deviation of the

project duration, σ =

[Σ [V (ij)]] ^ (1/2) for the critical path

 

Step: 5

Probability of completing the project in T days

= P(X ≤ T)

= P (Z ≤ (T − μ)/σ)

 

  Where,

Z      =

(X μ)/σ and

X      =

Random Variable for Expected Completion Time of the Project following Normal Probability Distribution.

 



Part B



YouTube link for the video on the above discussions including solution of the following illustration –




Please click on the following YouTube Link:



Project Management - PERT





PERT –

Computation of Expected Project Completion Time

 

Illustration:

A project consists of nine activities which are indicated by A, B, C etc. Their time estimates and precedence relationship are given below:

 

 

Time estimates (in days)

Activity

Preceding activity

Optimistic

Most likely

Pessimistic

A

4

6

8

B

A

5

7

15

C

A

4

8

12

D

B

15

20

25

E

B

10

18

26

F

C

8

9

16

G

E

4

8

12

H

D, F

1

2

3

I

G, H

6

7

8

 

You are required to –

1.    Draw the network diagram,

2.    Determine the critical path and compute the expected project        completion time, and

3.    Determine the probability of completing the project in 55 days.


1 comment:

  1. This article is very well explained and student friendly. It was very helpful for my CMA inter exam.

    ReplyDelete