Project Management
Critical Path Method
– DETERMINATION OF FLOATS
Part B: YouTube link for the video on the above discussions including solution of one illustration involving –
i) Drawing the Network Diagram,
ii) Calculating the earliest start (ES),
earliest finish (EF), latest start (LS), and latest finish (LF) of each of the
activities, and
iii) Determining the different floats of the activities of
a project.
Part A
DEFINITION OF FLOATS
In project management (where management
of the project involves network analysis through network diagram), while
exercising control over time, resources, or cost, it is necessary to know as to
what flexibility exists for scheduling the non-critical activities of the
project. This flexibility that any activity has is termed as “float”.
Therefore, in project management, “float”, sometimes also referred to as “slack”,
is a number that indicates the amount of time a task can be delayed without
impacting the subsequent tasks and the project’s overall completion time. It’s
important to keep track on the floats when a project schedule is maintained for
managing the project in a better way. Floats are the key pieces of the critical
path method (CPM), a system used by project managers to efficiently schedule
the project activities.
It is important to take note here that
the critical activities of a project have no float. Work on non-critical
activities, on the other hand, may be postponed for sometime without affecting
the project duration.
There are four types of floats in
project management as follows:
1. Total Float,
2. Free Float,
3. Independent Float, and
4. Interfering Float.
1.
Total Float
The
total float of an activity represents the amount of time by which it can be
delayed without delaying the project completion date. In other words, it refers
to the amount of free time associated with an activity which can be used
before, during or after the performance of this activity.
2.
Free Float
The
free float is that part of the total float which can be used without affecting
the float of the succeeding activities.
3.
Independent Float
The
independent float of an activity is the amount of float time which can be used
without affecting either the head or the tail events.
4.
Interfering Float
The
interfering float of an activity is that part of the total float which causes a
reduction in the float of the successor activities.
DETERMINATION OF FLOATS
Steps for determining the floats
Step: 1 – Drawing the Network Diagram with durations of
the activities
Step: 2 – Identifying the Earliest Start (ES) and Latest
Finish (LF) for each of the nodes of the diagram
Step: 3 – Identifying the Earliest Start (ES), Earliest
Finish (EF), Latest Start (LS), Latest Finish (LF), Head Slack and Tail Slack for
each of the activities of the diagram with the help of the following chart and
the formulas
Step: 4 – Determining
the floats for each of the activities
Total Float (three formulas)
1 |
LF of present activity – EF of present activity |
2 |
LS of present activity – ES of present activity |
3 |
LF of present activity – ES of present activity − d |
Free Float (two formulas)
1 |
ES of following activity − EF of present activity |
2 |
Total Float − Head Slack of present activity |
Independent Float (two formulas)
1 |
ES of following activity − LF of preceding activity − d |
2 |
Free Float – Tail
Slack of present activity |
Interfering Float (two formulas)
1 |
LF of present activity – ES of following activity |
2 |
Head Slack of present activity |
YouTube link for the video on the above discussions including solution of the following illustration.
Please click on the following YouTube Link:
Project Management - Critical Path Method - Determination of Floats
Critical Path Method
Determination of Floats
Illustration:
Information on the
activities required for a project is as follows:
Activity |
Duration (days) |
1 – 2 |
2 |
1 – 3 |
7 |
1 – 4 |
8 |
2 – 5 |
3 |
3 – 5 |
6 |
3 – 6 |
10 |
3 – 7 |
4 |
4 – 6 |
6 |
5 – 7 |
2 |
6 – 8 |
5 |
7 – 8 |
6 |
You are required to –
1.
Draw the network diagram,
2. Calculate the earliest start (ES), earliest finish (EF), latest start
(LS), and latest finish (LF) of each of the activities, and
3.
Determine for each of the activities –
(i)
Head
Slack,
(ii)
Tail
Slack,
(iii)
Total
Float,
(iv)
Free
Float,
(v)
Independent
Float, and
(vi)
Interfering
Float.
No comments:
Post a Comment